Chapter 1 Preliminary
1 Name of Regulation
This Regulation is the Protection of the Environment Operations (General) Regulation 1998.
2 Commencement
This Regulation commences on the commencement of the Act.Editorial note—The Act commenced on 1.7.1999.
3 Definitions
(1) In this Regulation:the Act means the Protection of the Environment Operations Act 1997.the Approved Methods Publication means:(a) in relation to air pollutants—the document entitled “Approved Methods for the Sampling and Analysis of Air Pollutants in New South Wales” prepared by the EPA and published in the Gazette, as in force from time to time, or(b) in relation to water pollutants—the document entitled “Approved Methods for the Sampling and Analysis of Water Pollutants in New South Wales” prepared by the EPA and published in the Gazette, as in force from time to time.(2) Terms used in Schedule 1 to this Regulation that are defined in Schedule 1 to the Act have the same meanings as they have in Schedule 1 to the Act.cl 3: Am 2008 (109), Sch 2 [1].
4 Notes
The explanatory note, table of contents and notes in the text of this Regulation do not form part of this Regulation.
Chapter 2 Licensing
Part 2.1 Licence fees
Division 1 Preliminary
5 Definitions
(1) In this Part and Schedule 1:actual load of an assessable pollutant means the actual load calculated as referred to in clause 18 (2).administrative fee means the fee calculated in accordance with Division 3 and Schedule 1.agreed load means a load agreed to pursuant to a load reduction agreement with the EPA in accordance with Division 5.air pollutant means a pollutant specified as an air pollutant in the Table to clause 20.assessable pollutant means an air pollutant or water pollutant specified in relation to an activity in Schedule 1.fee rate threshold means the amount of an assessable pollutant that may be discharged in any licence fee period before the fee rate for any further discharge of the assessable pollutant increases.fee unit—see clause 6.licence fee period—see clause 7.load means the mass or quantity of a pollutant.load-based fee means the fee calculated in accordance with clause 23.summer period, in relation to the calculation of a load-based fee for a licence, means all the days during the licence fee period for the licence that occur during the months of December, January or February.Sydney basin area means the local government areas of Ashfield, Auburn, Bankstown City, Baulkham Hills, Blacktown City, Botany Bay City, Burwood, Camden, Campbelltown City, Canada Bay, Canterbury City, Fairfield City, Hawkesbury City, Holroyd City, Hornsby, Hunter’s Hill, Hurstville City, Kogarah, Ku-ring-gai, Lane Cove, Leichhardt, Liverpool City, Manly, Marrickville, Mosman, North Sydney, Parramatta City, Penrith City, Pittwater, Randwick City, Rockdale City, Ryde City, Strathfield, Sutherland Shire, City of Sydney, Warringah, Waverley, Willoughby City and Woollahra.water pollutant means a pollutant specified as a water pollutant in the Table to clause 20.weighted load of an assessable pollutant means the actual load, adjusted, if appropriate, for load weighting measures specified in a load calculation protocol for an activity as referred to in clause 18 (3).(2) In this Part, a reference to the EPA is a reference to the EPA in its capacity as the appropriate regulatory authority. If some other authority is the appropriate regulatory authority in respect of a particular activity, a reference to the EPA in relation to that activity is to be construed as a reference to that regulatory authority.Note—Section 6 of the Act provides that the EPA is the appropriate regulatory authority for the purposes of the Act, with certain exceptions. In respect of the matters to which this Part applies, the EPA is the appropriate regulatory authority unless some other regulatory authority is declared by the regulations to be the appropriate regulatory authority for the activity concerned. At the commencement of the Act, no other regulatory authority had been so declared by the regulations.cl 5: Am 2007 (295), Sch 1 [1].
6 Fee units
(1) There are 2 types of fee unit for the purposes of this Part:(a) an administrative fee unit, and(b) a pollutant fee unit.(2) The amount of a fee unit is to be determined for any licence fee period in accordance with the following Table:Table
Date when licence fee period for licence begins Administrative fee unit amount Pollutant fee unit amount 1 July 1999 to 30 June 2000 $50 $0 1 July 2000 to 30 June 2001 $95 $24 1 July 2001 to 30 June 2002 $95 $29 1 July 2002 to 30 June 2006 $95 $35 1 July 2006 to 30 June 2007 $95 $36.75 1 July 2007 to 30 June 2008 $100 $36.75 1 July 2008 or subsequently $100 $38.61(3) For the purposes of subclause (2), the date on which the licence fee period begins in respect of an application for the issue of a licence is the date on which the application is made.(4) (Repealed)cl 6: Am 2007 (295), Sch 1 [2] [3]; 2008 (109), Sch 2 [2]; 2009 (210), Sch 2.
7 Licence fee period
(1) For the purposes of this Part, the licence fee period for a licence is the period of 12 months after the issue of the licence and each subsequent period of 12 months, subject to this clause.(2) The licence fee period is not affected by any transfer of the licence.(3) A licence fee period comes to an end if the licence ceases to be in force (but not if the licence is suspended).(4) In the case of a licence issued under a repealed Act (or provision) and continued in force at the commencement of the Act, the first licence fee period is the period of 12 months commencing on:(a) the first anniversary, after the commencement of the Act, of the date of the issue of the licence, or(b) if the licence was renewed, the first anniversary, after the commencement of the Act, of the date of last renewal of the licence before that commencement.(5), (6) (Repealed)cl 7: Am 25.6.1999.
7A Changes in licence fee period
(1) The EPA may, by notice in writing given to the licensee, change the licence fee period for a licence applicable under clause 7 for the purpose of providing a common licence fee period for different licences held by the same person or for other good cause. Any such notice has effect according to its tenor.(2) The EPA may change a licence fee period on the application of the licensee or on its own initiative. The EPA may decline to deal with any such application unless the licensee pays to the EPA such reasonable fee as the EPA determines to cover the cost of dealing with the application.(3) If a licence fee period is changed under this clause, the total of the licence fees for the licence in respect of all the periods affected by the change is, despite anything to the contrary in this Regulation, to be the same as it would have been if the change had not been made. Accordingly, the EPA is to make any necessary refunds in respect of fees already paid or require the payment of any additional amount of fees for relevant periods.(4) This clause extends to an existing licence referred to in clause 7 (4).cl 7A: Ins 25.6.1999.
Division 2 Licence fees generally
8 Types of licence fees
This Part applies to the following 2 types of licence fees payable under the Act:(a) fees required to accompany applications for the issue of licences, and(b) annual licence fees to be paid by the holders of licences.Note—Section 53 (2) (c) of the Act provides for application fees for the issue of licences and section 57 of the Act provides for annual licence fees. See clause 48 for fee payable on application for transfer of licence.
9 Initial basis for determining licence fees
As a first step, the fee for a licence is to be determined according to the activity carried out or proposed to be carried out by the holder of the licence. The classification of activities for the purpose of determining licence fees is found in Schedule 1.
10 The main elements of licence fees
For all licences there is payable:(a) an administrative fee determined according to the activity carried out or proposed to be carried out by the holder of the licence in accordance with Division 3 and Schedule 1, and(b) in respect of a licence relating to an activity listed in Schedule 1 for which one or more assessable pollutants are identified in that Schedule, a load-based fee determined in accordance with clause 23.
11 Licence fees prescribed for purposes of Act
(1) The licence fees prescribed for the purposes of the Act are as follows:(a) in the case of the fee to accompany an application for the issue of a licence (section 53 (2) (c))—the relevant administrative fee for the licence,(b) in the case of the annual licence fee payable by the holder of the licence (section 57 (1))—the relevant administrative fee for the licence and, if applicable, the additional component of the relevant load-based fee for the licence.(2) Despite subclause (1) (b), an administrative fee is not payable as part of the annual licence fee in respect of the first licence fee period of a licence first issued after the commencement of the Act.(3) Despite subclause (1) (b), a load-based fee is not payable for a supervisory licence referred to in section 87 of the Act.Note—The annual licence fee is payable, in respect of the administrative fee component, within 60 days after the beginning of the licence fee period and, in respect of the load-based fee component, within 60 days after the end of the licence fee period (see Division 6). An additional amount of annual licence fees is payable for special licences as a transitional measure (see Division 9).
Division 3 Administrative fees
12 Administrative fees generally
The administrative fee for a licence is the number of administrative fee units for the activity authorised or controlled by the licence determined in accordance with this Division and Schedule 1.
13 Licences relating to more than one activity
If a licence relates to more than one of the activities listed in Schedule 1, the administrative fee payable is the higher or highest of the administrative fees for those activities determined in accordance with this Division and Schedule 1.
14 Refunds—application fees
(1) The EPA may refund the payment of all or any part of an administrative fee that accompanies an application for the issue of a licence if the EPA refuses the application. The EPA is to have regard to the administrative costs incurred by the EPA in connection with the application.(2) An application for any such refund may only be made within 90 days after the applicant is notified of the refusal of the application.(3) The EPA may extend the time for making an application for any such refund if it is satisfied there is good cause for doing so.
15 Refunds and waivers—annual licence fees
(1) The EPA may refund the payment of all or any part of an administrative fee that is an annual licence fee if the EPA considers that it is appropriate to do so having regard to the administrative costs incurred by the EPA in connection with the licence.(2) Without limiting subclause (1), the EPA may make any such refund of the difference between the administrative fee paid and any lesser amount that would have been payable if the administrative fee had been calculated on the actual level of the activity during the licence fee period to which the fee relates.(3) An application for any such refund may only be made within 90 days after the end of the licence fee period to which the fee relates.(4) The EPA may extend the time for making an application for any such refund if it is satisfied there is good cause for doing so.(5) Without limiting the other provisions of this clause, on approval of an application under section 80 of the Act for surrender of a licence, the EPA may waive the payment of all or any part of an administrative fee that is an annual licence fee in respect of the licence concerned if the EPA considers it appropriate to do so having regard to the administrative costs incurred by the EPA in connection with the licence.cl 15: Am 2004 No 55, Sch 1.21 [1] [2].
Division 4 Load-based fees
16 Object of this Division
(1) The object of this Division is to give effect to a Load-Based Licensing Scheme to provide continuing incentives that will encourage persons licensed under the Act to reduce pollution in a cost effective and timely manner.(2) The objects of the Scheme are as follows:(a) to provide incentives to reduce emissions of pollutants based on the polluter pays principle and to apply them within an equitable framework,(b) to give industry incentives for ongoing improvements in environmental performance and the adoption of cleaner technologies,(c) to provide incentives that are complementary to existing regulation and education programs for environment protection.
17 Factors relevant to determination of load-based fee
The factors relevant to the determination of the load-based fee for a licence include the following:Note—There are three broad steps to calculating the load-based fee for a licence:1 calculating the fee for each assessable pollutant, and2 totalling those assessable pollutant fees, and3 subtracting the amount of the correct administrative fee (payable under clause 29 after the beginning of the licence fee period).(a) the kind of activity (determined in accordance with Schedule 1),(b) the kinds of pollutants discharged (the assessable pollutants being those listed in Schedule 1),(c) the assessable load of each assessable pollutant discharged (determined in accordance with clauses 17A (where relevant) and 18),(d) the appropriate pollutant weightings (determined in accordance with clause 20),(e) the appropriate pollutant critical zone weightings (determined in accordance with clause 21),(f) the appropriate fee rate thresholds (determined in accordance with clause 22),(g) the terms of any load reduction agreement entered into with the EPA by the applicant (under Division 5).cl 17: Am 2007 (295), Sch 1 [4].
17A Calculation of load-based fees in relation to nitrogen oxides and VOCs discharged from premises in Sydney basin area in summer
For the purposes of applying the provisions of this Part and Schedule 1 to the calculation of load-based fees, a licensee who discharges nitrogen oxides or VOCs from premises in the Sydney basin area during the summer period for the licensee’s licence must:(a) treat the discharge as a separate and distinct discharge of an assessable pollutant from the discharge of such a pollutant during the whole of the licence fee period, and(b) apply any weightings or fee rate threshold factors indicated by “nitrogen oxides (summer)” or “VOCs (summer)” instead of the weightings or threshold factors for calculations for the whole licence period that are indicated by “nitrogen oxides” or “VOCs” alone, and(c) in addition to paragraphs (a) and (b)—include the discharge in calculating the discharge of such a pollutant during the whole of the licence fee period.Note—The above provisions effectively require a licensee to count any discharge of nitrogen oxides or VOCs from premises in the Sydney basin area during the summer period for the licence twice, once in its own right and then as part of the discharge for the whole licence fee period.cl 17A: Ins 2007 (295), Sch 1 [5].
18 Determination of assessable loads of assessable pollutants
(1) Licensee must calculate actual load A licensee must calculate the actual load for each assessable pollutant discharged under the licensee’s licence during the licence fee period (whether or not the pollutant was discharged in accordance with the licence). For that purpose, the licensee must carry out all necessary monitoring and other steps to enable the calculation to be made for the relevant period.(1A) Calculation of actual load for nitrogen oxides and VOCs during summers periods in Sydney basin area In addition to the calculation required by subclause (1), a licensee must (if relevant to the licensee) also calculate the actual load for nitrogen oxides or VOCs discharged from premises in the Sydney basin area under the licensee’s licence (whether or not discharged in accordance with the licence) during the summer period for the licence. For that purpose, the licensee must carry out all necessary monitoring and other steps to enable the calculation required by this subclause to be made.(2) Actual load calculated using methods in protocols The actual load must be calculated using any of the methods provided in the load calculation protocol for the relevant activity issued by the EPA and in force. If there is no such protocol, the actual load for each assessable pollutant is taken to be zero.(3) Issue of load calculation protocols For the purpose of this Division, the EPA may from time to time issue, or vary, load calculation protocols by notice published in the Gazette. Without limiting the matters that may be dealt with in a protocol, such a protocol may:(a) set out the means for calculating actual loads and weighted loads, including by the use of monitoring programs, emission factors and other methods, andNote—An emission factor may be used to estimate the level of emissions generated by an activity. The factor relates the level of emissions expected to be generated relative to another characteristic of the activity, such as user-specified control technologies or techniques or the area of land disturbed. For example, an emission factor for the discharge of phosphorous from a small sewage treatment plant where chemical dosing and tertiary filters are installed might be 1mg for every litre of wastewater treated.(b) provide for load weighting measures, such as:(i) ceasing or reducing discharges during particularly unfavourable conditions, and(ii) reusing waste water (whether by the licensee or another person), and(c) provide for a reduction in the actual load of a licensee:(i) where any assessable pollutants are transferred, without being discharged, from the premises of a licensee to the premises of another person with the consent of the other person, or(ii) where a licensee receives onto the licensee’s premises naturally occurring loads of assessable pollutants, and(d) provide for any such reduction in the actual load of a licensee arising from the transfer of assessable pollutants to another person’s premises to be subject to arrangements for the payment by that other person to the EPA of the amount of any reduction in the load-based fee payable by the licensee as a result of the transfer,(e) provide for a reduction in the actual load of a licensee by permitting a notional reduction of the amount of an assessable pollutant discharged in the relevant period by reference to a reduction in the discharge of that pollutant (elsewhere than at the premises where the activity is carried on) as a result of action taken by the licensee in connection with that activity.Note—An example of such a protocol could be the emission of VOCs by an oil refinery. In addition to action to reduce those emissions from the refinery, action can be taken to produce fuel that will emit less VOCs when in use off the premises of the refinery.(4) A protocol takes effect in relation to an activity from the date specified in the protocol and from that date any previous protocol in relation to the activity ceases to have effect.(5) Licensee must calculate weighted load according to appropriate protocol A licensee who calculates a weighted load must use the methods provided in the load calculation protocol for the activity.(6) Assessable load used for load-based fee calculation The assessable load to be used for the load-based fee calculation for each assessable pollutant is the least of the actual load or weighted load calculated in accordance with this clause or an agreed load calculated in accordance with Division 5 for that pollutant.(7) Availability of protocols A copy of any protocol in force under this clause must be available for inspection and purchase by members of the public at the principal office of the EPA. The purchase price may be any reasonable amount that the EPA determines.(8) Transitional A licensee is, in relation to a licence fee period that begins during the period 1 July 1999 to 30 June 2000, required to make calculations (and carry out monitoring and other steps for calculations) under this clause with respect to the calculation of load based licensing fees for which a load based-fee would have been payable but for the prescription under clause 6 of a pollutant fee unit of $0.cl 18: Am 25.6.1999; 2007 (295), Sch 1 [6].
19 Determination of load-based fee where insufficient information provided by licensee
(1) If insufficient information is given to the EPA by a licensee to enable the EPA to confirm the correct amount of a load-based fee within 60 days after the final date for payment of the fee, the EPA may determine the amount of the load-based fee having regard to such information, if any, as is available to it.(2) The amount so determined is taken to be the correct amount of the fee unless the contrary is established by the person liable to pay the fee in any proceedings for the recovery of the fee or other relevant proceedings relating to the fee.
20 Pollutant weightings
(1) The pollutant weightings for air pollutants and water pollutants (as defined in the following Table) are the weightings (per unit mass) specified in the Table.Table
Air pollutants Pollutant Definition Pollutant weighting Arsenic Total arsenic calculated using the method prescribed in the Approved Methods Publication 52,000 Benzene Benzene 740 Benzo[a]pyrene (equivalent) Benzo[a]pyrene plus 0.1 times the mass of benzo[a]anthracene, benzo[b]fluoranthene, benzo[k]fluoranthene and ideno[1,2,3-c,d]pyrene plus 0.4 times the mass of dibenz[a,h]anthracene 29,000 Coarse particulates All solid particulates entrained in air but not including fine particulates as defined in this Table 18 Fine particulates The fraction of all solid particulates entrained in air with an aerodynamic diameter smaller than 10 micrometres 125 Fluoride Fluorine, hydrogen fluoride and all other inorganic fluoride compounds expressed as hydrogen fluoride equivalent 84 Hydrogen sulfide Hydrogen sulfide 320 Lead Total lead calculated using the method prescribed in the Approved Methods Publication 11,000 Mercury Total mercury calculated using the method prescribed in the Approved Methods Publication 110,000 Nitrogen oxides and Nitrogen oxides (summer) The sum of nitrogen oxide and nitrogen dioxide expressed as nitrogen dioxide equivalent 9 Sulfur oxides Sulfur dioxide and (where specified in the load calculation protocol for the activity or in the licence for the premises) sulfur trioxide and sulfuric acid mist 2.2 VOCs and VOCs (summer) Volatile compounds of hydrogen and carbon that may or may not contain other elements but not including methane or benzene 6.6
Water pollutants Pollutant Definition Pollutant weighting Open coastal waters Estuarine waters Enclosed waters Arsenic Total arsenic calculated using the method prescribed in the Approved Methods Publication 2,500 2,500 2,500 BOD5 Biochemical oxygen demand calculated using the method prescribed in the Approved Methods Publication 0 0.5 1 Cadmium Total cadmium calculated using the method prescribed in the Approved Methods Publication 67,000 67,000 67,000 Chromium All trivalent chromium plus ten times hexavalent chromium, whether present in elemental form or contained in compounds or complexes 840 4,200 4,200 Copper Total copper calculated using the methods prescribed in the Approved Methods Publication 1,700 1,700 1,700 Lead Total lead calculated using the method prescribed in the Approved Methods Publication 6,400 6,400 6,400 Mercury Total mercury calculated using the method prescribed in the Approved Methods Publication 180,000 180,000 180,000 Oil and grease Oil and grease calculated using the method prescribed in the Approved Methods Publication 13 30 74 Pesticides and PCBs The sum of aldrin, chlordane, DDE, DDT, dieldrin, endosulphan (a,b), heptachlor, lindane, PCBs, chlorpyrifos, diazinon, malathion and parathion 930,000 930,000 930,000 SaltNote—The pollutant weighting for salt is zero where the salt is discharged into naturally salty surface waters with an electrical conductivity of more than 10,000 micro siemens per centimetre Total dissolved solids calculated using the conductivity method prescribed in the Approved Methods Publication, or using a method provided in a load calculation protocol for the activity published by the EPA 0 0 8.4 Selenium Total selenium calculated using the methods prescribed in the Approved Methods Publication 710 10,000 10,000 Total nitrogen Total nitrogen calculated using the method prescribed in the Approved Methods Publication 6 12 23 Total PAHs The total of polyaromatic hydrocarbons 3,800 3,800 3,800 Total phenolics Total phenolic compounds calculated using the method prescribed in the Approved Methods Publication 4,900 4,900 4,900 Total phosphorous Total phosphorous calculated using the method prescribed in the Approved Methods Publication 0 120 680 Total suspended solids Non-filterable solids calculated using the method prescribed in the Approved Methods Publication 9.5 9.5 78 Zinc Total zinc calculated using the method prescribed in the Approved Methods Publication 7 7 7(2) In this clause:enclosed waters means all waters other than open coastal waters or estuarine waters.estuarine waters means waters (other than open coastal waters):(a) that are ordinarily subject to tidal influence, and(b) that have a mean tidal range greater than 800 mm (being the average difference between the mean high water mark and the mean low water mark, expressed in millimetres, over the course of a year).open coastal waters has the meaning given by Schedule 5.(3) The amendment to the Table to subclause (1) made by the Protection of the Environment Operations (General) Amendment (Pollutant Weightings) Regulation 2004 applies in relation to licence fee periods ending on or after 30 June 2004.cl 20: Am 2.6.2000; 25.6.2004; 2007 (295), Sch 1 [7] [8].
21 Pollutant critical zone weightings
(1) The pollutant critical zone weightings for air pollutants and water pollutants discharged into a critical zone set out opposite the pollutants in the following Table are the weightings specified in the Table.Table
Critical zones for air pollutants Pollutant Local government areas in zone Weighting Nitrogen oxides and VOCs Local government areas in the Sydney basin area, Blue Mountains City, Kiama, Shellharbour City and Wollongong City 7 Nitrogen oxides (summer) and VOCs (summer) Local government areas in the Sydney basin area 28 Nitrogen oxides and VOCs Cessnock, Gosford, Lake Macquarie, Maitland, Muswellbrook, Newcastle, Port Stephens, Singleton, Wollondilly, Wyong 2
Critical zones for water pollutants Pollutant Catchments in zone Weighting Salt Benanee, Bulloo River, Castlereagh, Condamine/Culgoa, Cooper Creek, Darling, Lachlan, Lake Bancannia, Lake Frome, Macquarie River, Moonie, Murray Riverina, Murray (Lower), Murray (Upper), Murrumbidgee, Paroo, Warrego 3 Total phosphorous and total nitrogen Benanee, Border Rivers, Bulloo River, Castlereagh, Condamine/Culgoa, Cooper Creek, Darling, Gwydir, Hawkesbury-Nepean, Lachlan, Lake Bancannia, Lake Frome, Macquarie River, Moonie, Murray Riverina, Murray (Lower), Murray (Upper), Murrumbidgee, Namoi, Paroo, Warrego 3(2) The pollutant critical zone weighting for all pollutants other than those given a weighting by the Table is 1.(3) If a licence authorises or controls the discharge of pollutants into more than one critical zone, the critical zone weighting factor for those pollutants is the factor applicable to the zone into which the majority of the load is discharged. This subclause applies separately to air pollutants and to water pollutants.(4) The catchments referred to in the Table are the catchments as shown on the maps marked “Catchments of NSW displayed for the purpose of Load-Based Licensing” deposited in the office of the EPA.cl 21: Am 2007 (295), Sch 1 [9].
22 Calculation of fee rate thresholds for assessable pollutants
(1) The steps to be taken to determine the fee rate threshold for the licence fee period for each assessable pollutant for an activity are as follows:Step 1Select the applicable fee rate threshold factor for the pollutant for the activity from Schedule 1.Note—Fee rate threshold factors are expressed in units of kilograms of pollutants per the applicable unit of quantity of activity.The discharge of nitrogen oxides or VOCs from premises in the Sydney basin area during the summer period for a licence is to be treated as a separate and distinct discharge of an assessable pollutant from the discharge during the whole licence fee period. See clause 17A.Step 2Determine the actual quantity of activity during the licence fee period, calculated using the units of measure for the activity specified in respect of the activity in Schedule 1.Step 3Multiply the fee rate threshold factor selected in Step 1 by the quantity of activity determined in Step 2.(2) If more than one classification in Schedule 1 applies, the fee rate threshold for each assessable pollutant is the sum of the fee rate thresholds for each applicable classification of activity calculated in accordance with this clause.cl 22: Am 2007 (295), Sch 1 [10].
23 Calculation of load-based fee
The steps to determine the load-based fee in relation to a licence are as follows:Step 1Determine the classification or classifications of the activity.Note—Refer to the activity classifications in Schedule 1.Step 2Determine if there are any assessable pollutants for the activity classification. If more than one activity classification is applicable, the assessable pollutants are those applying to each classification.Note—Refer to the list of assessable pollutants under each activity classification in Schedule 1. If there are no assessable pollutants, no load-based fee is payable in relation to the activity.Step 3Determine the assessable load of each assessable pollutant. The assessable load is the least of the actual load or the weighted load (determined in accordance with clause 18) or the agreed load (determined in accordance with Division 5).If more than one classification in Schedule 1 applies, the assessable load for each assessable pollutant is the sum of the assessable loads of that assessable pollutant for each applicable classification of activity calculated in accordance with this clause.Note—The assessable load for the discharge of nitrogen oxides or VOCs from premises in the Sydney basin area during the summer period for a licence is to be calculated in addition to the assessable load for the discharge of such a pollutant during the whole licence fee period. See clauses 17A and 18 (1A).Step 4Calculate the fee rate thresholds for each assessable pollutant.Note—The method for calculating the fee rate thresholds is set out in clause 22.Step 5Calculate the fee for each pollutant. The fee for each pollutant is calculated using one of the formulas shown below. If the assessable load determined in Step 3 is greater than the fee rate threshold calculated in Step 4, use Formula 1. In all other cases, use Formula 2.Formula 1
Fee (if the assessable load is greater than the fee rate threshold) =Formula 2
Fee (in all other cases) =where:AL= assessable load of the assessable pollutant discharged, expressed in kilograms (see Step 3 above).CZ= pollutant critical zone weighting for the assessable pollutant (see clause 21).FRT= the applicable fee rate threshold, expressed in kilograms (see Step 4 above).PFU= the amount equal to one pollutant fee unit specified in clause 6 for the assessable pollutant.PW= pollutant weighting for the assessable pollutant (see clause 20).Step 6Total the fees for each assessable pollutant.Step 7Subtract the amount of the administrative fee (excluding the amount of any increase in the administrative fee as a penalty for the late payment of the fee).Despite anything else in this clause, the amount of the load-based fee can never be negative.cl 23: Am 2007 (295), Sch 1 [11].
24 Refunds—errors in calculations
A person who, in payment of a load-based fee, pays, because of an error in calculation of the assessable load, an amount that is greater than the load-based fee is entitled to a refund of the amount overpaid.
Division 5 Load reduction agreements and fee reductions
pt 2.1, div 5, hdg: Am 1.6.2001.
24A Definitions
In this Division:agreed load means the agreed load, in respect of a licence fee period, for an assessable pollutant under a load reduction agreement applicable to that pollutant.load reduction agreement means a load reduction agreement entered into under this Division.reported load means:(a) the actual load that is reported to the EPA by a licensee for an assessable pollutant for a licence fee period (unless paragraph (b) applies), or(b) if a weighted load is reported to the EPA by the licensee for the assessable pollutant for the licence fee period—the weighted load.cl 24A: Ins 1.6.2001. Am 1.8.2003.
25 Load reduction agreements and fee reductions
(1) A licensee or applicant for a licence may, for the purpose of obtaining a reduction of the load-based fee payable for a licence, apply to the EPA to enter into a load reduction agreement with it.(2) An application for a load reduction agreement is to be in or to the effect of a form approved by the EPA.(3) The EPA may enter into or decline to enter into a load reduction agreement.(4) Without limiting the circumstances in which the EPA may decline to enter into a load reduction agreement, it may do so if:(a) the agreement is unlikely to produce a fee reduction of $2,000 or more over the term of the agreement, or(b) the licensee or applicant proposes to reduce its discharge at the end of the agreement only because the licensee or applicant proposes to close or reduce the scale of operations being conducted at that time.(5) The provisions of a load reduction agreement may be amended by consent between the person who has entered into the agreement (or, in the case of a licence that is transferred, the transferee) and the EPA.(6) The maximum term of a load reduction agreement is 4 years.cl 25: Am 1.6.2001.
25A Effect of transfer of licences on load reduction agreements
(1) If a person who has entered into a load reduction agreement transfers the relevant licence, the transferee is, for the purposes of the agreement and this Regulation, taken to be a person who has entered into the agreement with the EPA.(2) A transferee may elect, on the transfer of the licence, to terminate the load reduction agreement and clauses 28, 28B and 28C apply to that termination.cl 25A: Ins 1.6.2001.
26 Content of load reduction agreements
(1) A load reduction agreement must:(a) specify the agreed load for an assessable pollutant for each licence fee period of the agreement, and(b) specify the program proposed to be undertaken in order to attain the agreed load, and(c) require the licensee to notify the EPA if the licensee becomes aware that it is likely that the licensee will not be able to attain the agreed load under the agreement, and(d) set out the circumstances in which amounts are to be paid to the EPA on termination or expiry of the agreement, and(e) provide that the agreement has no effect unless the licensee’s licence is subject to a condition that, on termination or expiration of the agreement, the total load that may be emitted in respect of a licence fee period for an assessable pollutant that was covered by the agreement is to be:(i) the same as the agreed load under the agreement, if the reported load for the pollutant for the licence fee period immediately preceding the termination or expiration did not exceed the agreed load, or(ii) an amount determined by the EPA, after consultation with the licensee, that is higher than the agreed load, if the reported load for that period exceeded the agreed load.(2) A load reduction agreement may require a financial assurance to be supplied by the licensee to secure obligations in the event of termination or expiration of the agreement and must, in any such case, provide for the following matters:(a) the circumstances in which the EPA may make a claim on or realise the financial assurance or part of it,(b) that the calling on and use of a financial assurance does not affect any liability of the licensee,(c) the effect of failure to provide a financial assurance.(3) A financial assurance may be in one or more of the following forms:(a) a bank guarantee,(b) a bond,(c) another form of security that the EPA considers appropriate and specifies in the load reduction agreement.cl 26: Subst 1.6.2001. Am 1.8.2003.
27 Calculation of reduction
(1) For the purposes of this Division, the reduction of a licence fee in relation to a licence fee period is the difference between the amount payable under the load reduction agreement in respect of an assessable pollutant and the amount that would have been payable for that licence fee period, but for the agreement.(2) If, at the end of the agreement, a licensee has closed its operations or has otherwise ceased to operate, the licensee:(a) is taken to have failed to meet the agreed load, and(b) must pay to the EPA the amounts of all reductions of licence fees under the agreement and the amount of simple interest on each amount calculated weekly at the rate of 20% per annum from the date on which the reduced amount was payable.cl 27: Am 1.6.2001.
28 Termination of agreement
(1) The licensee may terminate the load reduction agreement before the end of the term of the agreement in accordance with the agreement.(2) If a licence is surrendered by the licensee or suspended or revoked, any load reduction agreement relating to licence fees for the licence is taken to have been terminated by the licensee.(3) The EPA may terminate a load reduction agreement if:(a) the EPA is of the opinion that the licensee is unlikely to attain the agreed load before the end of the agreement, or that the licensee is unlikely to meet the costs of repayment on termination or expiration of the agreement, or both, or(b) the licensee fails to comply with a condition of the agreement.(4) A licensee that terminates a load reduction agreement, or whose agreement is terminated, is not liable to pay an amount on termination in respect of an assessable pollutant if the reported load for the immediately preceding licence fee period did not exceed the agreed load for the pollutant under the agreement.(5) A licensee that terminates a load reduction agreement, or whose agreement is terminated, must pay to the EPA the amounts calculated in accordance with clause 28B if the reported load for the immediately preceding licence fee period exceeded the agreed load for the pollutant under the agreement.cl 28: Subst 1.6.2001. Am 1.8.2003.
28A Liability of licensee on expiration of agreement
(1) On the expiration of a load reduction agreement the licensee must pay to the EPA, in respect of an assessable pollutant covered by the agreement, the amounts required under this clause.(2) No amount is payable in respect of an assessable pollutant under this clause if the reported load for the immediately preceding licence fee period did not exceed the agreed load for the pollutant under the agreement.(3) If the reported load for the immediately preceding licence fee period exceeded the agreed load for the pollutant under the agreement, the licensee must pay to the EPA the amounts calculated in accordance with clause 28B.cll 28A: Ins 1.6.2001. Am 1.8.2003.
28B Amounts payable on termination or expiration
(1) The amounts payable on termination or expiration are as follows:(a) for any licence fee period during the agreement in which the reported load exceeded the maximum load, the difference between the fee that would have been payable for that period if the load had been equal to the agreed load under the agreement and the fee that would have been payable if the load had been equal to the maximum load,(b) for any licence fee period during the agreement in which the reported load for the pollutant did not exceed the maximum load, no amount is payable,(c) the amount of simple interest on an amount payable under this subclause calculated at the rate of 20% per annum from the date that is 60 days after the end of each licence fee period.(2) In this clause:maximum load means the total load limit for an assessable pollutant that is imposed as a condition of a licence on the termination or expiration of a load reduction agreement.cll 28B: Ins 1.6.2001. Am 1.8.2003.
28C When amounts must be paid
(1) An amount payable under clause 28 or 28A must be paid not later than 60 days after a written request for payment of the amount is given to the licensee by the EPA.(2) If the amount is not paid (or not fully paid) by the due date for its payment, the amount is to be increased by the amount of simple interest calculated at the rate of 5% per fortnight on the amount unpaid for each whole fortnight that elapses after the due date and before the date of payment.cl 28C: Ins 1.6.2001.
Division 6 Time for payment of licence fees and penalties for late payment
29 Administrative fee—time for payment
(1) The administrative fee for any licence fee period of a licence must be paid not later than 60 days after the beginning of that licence fee period.(2) This clause does not apply to an administrative fee that is required to accompany an application for the issue of a licence.
30 Penalty for late payment of administrative fee
(1) If an administrative fee is not paid (or not fully paid) by the due date for its payment, the administrative fee is to be increased by the amount of simple interest calculated at the rate of 5% per fortnight on the amount of the fee unpaid for each whole fortnight that elapses after the due date and before the date of payment.(2) Any such increased amount for an annual licence fee is prescribed as a penalty for the purposes of section 57 (4) of the Act.(3) This clause does not apply to an administrative fee that is required to accompany an application for the issue of a licence.cl 30: Am 2005 No 96, Sch 2.3 [1].
31 Load-based fee—time for payment
The load-based fee for any licence fee period must be paid within 60 days after the end of that licence fee period.
32 Penalty for late payment of load-based fee
(1) If a load-based fee is not paid (or not fully paid) by the due date for its payment, the load-based fee is to be increased by the amount of simple interest calculated at the rate of 5% per fortnight on the amount of the fee unpaid for each whole fortnight that elapses after the due date and before the date of payment.(2) Any such increased amount for an annual licence fee is prescribed as a penalty for the purposes of section 57 (4) of the Act.(3) The EPA may refund, or waive the payment of, the whole or any part of the amount of any increase of a load-based fee payable under this clause if satisfied that the licensee was unable to calculate and pay the fee by the due date because of circumstances beyond the control of the licensee. This subclause does not excuse the licensee from calculating and paying the load-based fee in respect of some of the pollutants concerned in so far as that calculation is not beyond the control of the licensee.cl 32: Am 2005 No 96, Sch 2.3 [2].
Division 7 Change in activity classification or scale during licence fee period
33 Application of this Division
This Division applies if an activity changes to an activity of a different classification or scale under Schedule 1 during the licence fee period.Note—This clause does not confer authority on a licensee to alter the classification or scale of an activity.
34 Adjustment of administrative fee
(1) The administrative fee for the licence is (if necessary) to be adjusted proportionately according to the parts of the licence fee period occurring before and after the change in the classification or scale of the activity.(2) No adjustment is to be made unless the resultant administrative fee is greater or less by at least $190 than the fee before adjustment.(3) Any additional amount of any fee already paid or due for payment is to be paid by the licensee to the EPA not later than 60 days after the change occurs.(4) Any reduction in the amount that is in excess of $190 is to be offset against any amount owed by the licensee to the EPA or otherwise refunded to the licensee by the EPA.(5) The provisions of Division 6 relating to the payment of interest on unpaid administrative fees applies to any additional amount of the fee under this clause.
35 Adjustment of load-based fee
The load-based fee for a licence is to comprise the sum of the load-based fee calculated for the part of the licence fee period occurring before the change in the classification or scale of the activity and the load-based fee calculated for the part of the licence fee period occurring after the change.
Division 8 Economic measures with respect to licence fees
36 Application
(1) This Division applies to a scheme involving economic measures of the kind referred to in this Division that is developed and implemented by the EPA under Part 9.3 of the Act.(2) This Division has effect subject to the terms of that scheme.(3) This Division does not limit any other scheme that may be developed and implemented under Part 9.3 of the Act.
37 Aggregation of licences for purpose of payment of licence fees—“bubble licence arrangements”
(1) The EPA may, under a scheme, approve of licence fees payable under 2 or more licences (whether or not held by the same person) being calculated by aggregating the assessable pollutants discharged in the relevant periods.(2) The EPA may terminate any such scheme at any time, whether because of a failure by the licensees to pay the relevant fees or otherwise. In that case, the licence fees for the relevant licence fee period are to be re-calculated and become payable for that period as if the scheme had not been established.
Division 9 Additional fee for special licences for transitional period
38 Application and definition
(1) This Division applies to special licences.(2) In this Division, a special licence is a licence:(a) that was in force on the commencement of the Act, and(b) for which the licence fee last payable before that commencement under the Pollution Control Act 1970 was more than $500,000.
39 Additional fee payable
(1) Each annual licence fee payable by the holder of a special licence for a licence fee period commencing before 1 July 2003 is to include an additional amount set out in the Table to this clause in respect of any such year.(2) Any such additional amount of an annual licence fee must be paid not later than the date set out in the Table to this clause in respect of that additional amount.(3) Clause 30 (Penalty for late payment of administrative fee) applies to any such additional amount of an annual licence fee in the same way as it applies to the administrative fee for the licence.Table
Period within which licence fee period commences Amount of additional fee Due date of additional fee 1 July 2000 to 30 June 2001 $3,850,000 1 June 2000 1 July 2001 to 30 June 2002 $2,850,000 1 June 2001 1 July 2002 to 30 June 2003 $2,000,000 1 June 2002
Part 2.2 Load-Based Licensing Technical Review Panel
40 Constitution of Review Panel
There is constituted by this Regulation a body corporate to be called the Load-Based Licensing Technical Review Panel.
41 Members of Review Panel
(1) The Review Panel is to have 7 members appointed by the Minister.(2) Of the members:(a) 2 are to be employees of the EPA nominated by the Director-General of the EPA, and(b) 5 are to be persons having appropriate scientific or technical qualifications or experience:(i) 2 of whom are to be representatives of industry, and(ii) one of whom is to be a representative of environment groups, and(iii) one of whom is to be a representative of the Director-General of the EPA, who is nominated by that Director-General and who is not an employee of the EPA or a representative of industry, environment groups or local government, and(iv) one of whom is to be a representative of local government.
42 Functions of Review Panel
(1) The Review Panel is to advise the EPA concerning the current or desirable contents of such load calculation protocols as the EPA may refer to the Review Panel.(2) The Review Panel may also advise the EPA on such other matters in connection with licences as the EPA may refer to the Review Panel.(3) For the purpose of providing any such advice, the Review Panel may seek, receive and consider submissions from interested persons and may gather relevant information from any source.
43 Membership and procedure of Review Panel
Schedule 2 has effect.
Part 2.3 Miscellaneous licensing provisions
43A Additional matters included in definition of “scheduled development work” for which licence required
Pursuant to section 47 (3) of the Act, the following is specified as scheduled development work for the purposes of the Act:Work at any premises at which scheduled activities of a class listed in Schedule 1 to the Act are carried on that is designed to enable scheduled activities of a different class not authorised by a licence to be carried on at the premises.cl 43A: Ins 25.6.1999.
44 Commencement of licensing requirement for existing activities not previously required to be licensed: sec 52 (1)
(1) The prescribed period for the purposes of section 52 (1) (a) of the Act is 9 months except as otherwise provided by this clause.(2) In respect of any work or activity that is associated with the work or activity to which an existing licence (within the meaning of the Protection of the Environment Operations (Savings and Transitional) Regulation 1998) applies, the prescribed period for the purposes of 52 (1) (a) of the Act is:(a) the period after the commencement of the Act and before a replacement licence takes effect under clause 10 of that Regulation (being a replacement licence that includes that associated work or activity), orwhichever is the shorter period.(b) 9 months,(3) The prescribed period in relation to sterilisation activities is the period ending 28 July 2008.Note—Sterilisation activities became licensable on 28 April 2008 as a consequence of the replacement of Schedule 1 to the Act by the Protection of the Environment Operations Amendment (Scheduled Activities and Waste) Regulation 2008.(4) The prescribed period after the commencement of the amendment to Schedule 1 to the Act made by the State Revenue and Other Legislation Amendment (Budget Measures) Act 2008 (to the extent that the amendment makes it necessary for a person to be authorised by a licence to continue to carry out an activity of composting or waste disposal by application to land for which a licence was not previously required) is 6 months.Note—Section 52 (1) of the Act postpones the need for a licence that is required by the enactment or amendment or replacement of Schedule 1 to the Act (Schedule of EPA-licensed activities) in order for a person to continue to carry out any work or activity. The need for the licence is postponed until the end of the prescribed period after the requirement for a licence arises or until a licence application is determined, whichever is the later.cl 44: Am 25.6.1999; 2008 (109), Sch 2 [3]–[5]; 2008 No 122, Sch 15.2.
45 Exclusion of Part 5 of EPA Act: sec 52 (2)
The EPA is not a determining authority within the meaning of Part 5 of the Environmental Planning and Assessment Act 1979 in respect of an approval (within the meaning of that Part) that consists of the issue of an environment protection licence referred to in section 52 (1) of the Protection of the Environment Operations Act 1997 so long as the licence authorises only the same or substantially the same work or activity, and level of work or activity, as was being carried out immediately before the application for the issue of the licence was made.
46 Matters to be set out in statement of reasons for grant or refusal of licence applications: secs 61 (2) (b), 80 (2A) (b)
(1) A statement provided by a regulatory authority under section 61 or 80 of the Act of the reasons for the grant or refusal of a licence application must set out the following matters (in addition to any other matters the authority considers appropriate):(a) the significant environmental or other issues that the authority took into account in making its decision on the licence application,(b) any significant environmental outcomes, standards or requirements (if relevant) that the authority considered applicable to the activity the subject of the application and that the authority took into account in making its decision on the application.(2) A statement of reasons may set out any of the above matters by reference to information set out in a document that is available to the person requesting the statement of reasons or that is otherwise publicly available.Note—Sections 61 and 80 of the Act require statements of reasons to be provided, on written request by any person, of the reasons for the grant or refusal of licence applications (namely, an application for the issue, transfer or variation of a licence or for the approval of the surrender of a licence).cl 46: Am 2002 No 14, Sch 5.4 [1] [2].
47 Offence of providing false information
(1) A person who, in or in connection with a licence application or an application under this Chapter, provides any information, or makes any statement, that is false or misleading in a material particular is guilty of an offence.Maximum penalty:(a) in the case of a corporation—200 penalty units,(b) in the case of an individual—100 penalty units.(2) It is a defence to a prosecution for an offence against this clause if the person establishes that the person had reasonable grounds to believe that the information or statement was true and had no reason to suspect that the information or statement was false or misleading in a material respect.
48 Transfer of licences
For the purposes of section 54 (2) (c) of the Act, the fee to accompany an application for the transfer of a licence is $190.Note—See clause 11 for fee payable on application for issue of licence.
49 Refusal of certain licence applications
(1) An application for the issue, transfer or variation of a licence, or for approval of the surrender a licence, may be refused by the appropriate regulatory authority:(a) if any fee or other amount due and payable under the Act or this regulation in relation to the application or licence is unpaid, or(b) if the applicant has previously defaulted in the payment of any such fee or other amount in respect of that or any other licence and the default continues.(2) This clause does not limit any other grounds on which the application may be refused.
49A Other relevant legislation: sec 83
(1) Pursuant to section 83 (5) of the Act, the following repealed Acts, provisions of Acts and Regulations are declared to be other relevant legislation for the purposes of section 83:(a) Clean Air Act 1961,(e) Pollution Control Act 1970,(f) the provisions of the Ozone Protection Act 1989 omitted by Schedule 4.14 to the Act,(g) the provisions of the Waste Minimisation and Management Act 1995 omitted by Schedule 4.19 to the Act,(h) regulations made under the above Acts or provisions.(2) Pursuant to section 83 (5) of the Act, the Pesticides Act 1978 and regulations made under that Act are declared to be other relevant legislation for the purposes of section 83 on and from the date that that Act is repealed by the Pesticides Act 1999.cl 49A: Ins 2.6.2000.
49B Protection of the Environment Operations (General) Amendment (Licensing Fees) Regulation 2007—transitional provisions
(1) The amendments made to this Regulation by the Protection of the Environment Operations (General) Amendment (Licensing Fees) Regulation 2007 relating to the calculation of load-based fees (including the amendment made by Schedule 1 [3] to that Regulation) extend to the licence fee periods ending on or after 30 June 2007.(2) For the avoidance of doubt, any condition in a licence in force immediately before 30 June 2007 that provides for load limits with respect to the discharge during the reporting period of nitrogen oxides or VOCs from premises in the Sydney basin area is varied so that those load limits are to be read as including the discharge of any such pollutant (referred to in this Regulation as nitrogen oxides (summer) or VOCs (summer)) from premises in the Sydney basin area during the summer period for the licence.cl 49B: Ins 2007 (295), Sch 1 [12].
50 Application of payments
If a person who makes a payment under this Chapter to the EPA does not identify the nature or purpose of the payment, the EPA may apply the payment towards any liability of the person under this Chapter in such manner as it thinks fit.
51 Preservation of records
(1) A licensee must retain all records used by the licensee to calculate the amount of a licence fee under Part 2.1 for a period of not less than 4 years from the date on which the fee was paid or payable, whichever is the later.Maximum penalty:(a) in the case of a corporation—200 penalty units,(b) in the case of an individual—200 penalty units.(2) A licensee is liable to a penalty under subclause (1) in addition to the licence fee.
Chapter 3 Water pollution
52 Prescribed matter for the definition of “water pollution” in Dictionary
The matter described in Schedule 3 is prescribed as matter for the purposes of paragraph (c) of the definition of water pollution in the Dictionary at the end of the Act.Note—The definition of water pollution for the purposes of the Act includes the placing etc into waters of any matter of a nature, description or class prescribed by the regulations or of matter that does not comply with a standard prescribed by the regulations in respect of that matter.
53 Methodology for testing for matter in waters
(1) This clause applies where a person is required by or under the environment protection legislation, or a licence or notice under that legislation, to test for the presence or concentration of matter in any waters.(2) The methodology for testing for the presence or concentration in waters of any matter is to be:(a) the methodology specified in the requirement for testing, or(b) if no such methodology is specified, the methodology prescribed in the Approved Methods Publication in relation to that matter.(3) The procedural details of any such methodology may be varied by the person conducting the test so long as the person can establish that the variation is not such as can affect the results of the test.(4) This clause does not apply to a person who is acting in the administration or execution of the environment protection legislation.
54 Exemption from water pollution offence for pollutants discharged from Victorian premises into River Murray
(1) Section 120 of the Act does not apply to a person who, from premises in Victoria, pollutes or causes or permits the pollution of the waters of the River Murray.(2) Subclause (1) applies only in relation to conduct that is authorised by a licence in force under the Environment Protection Act 1970 of Victoria.(3) The EPA may, by order in writing served on any such person, declare that the exemption arising under this clause no longer applies to the person in respect of pollution from those premises.(4) While such an order is in force, the exemption arising under this clause no longer applies to the person in respect of pollution from those premises.
55 Exemption from water pollution offence for pollutants discharged into sewer
(1) Section 120 of the Act does not apply to the discharge of pollutants into a sewer.(2) The exemption arising under this clause does not apply:(a) in the case of a sewer that is within the area of operations of a sewage authority, unless the discharge of the pollutants into the sewer has the approval of that authority, or(b) in any other case, unless the discharge of the pollutants into the sewer has the lawful approval of the person having the ownership or control of the sewer.(3) In this clause, means:(a) the Sydney Water Corporation Limited or the Hunter Water Corporation Limited, or(b) a water supply authority constituted under the Water Supply Authorities Act 1987, being an authority exercising sewerage functions under that Act, or(c) a council or county council exercising sewerage functions under Division 2 of Part 3 of Chapter 6 of the Local Government Act 1993.
55A Exemption from water pollution offence in relation to certified on-board sewage treatment systems
(1) Section 120 of the Act does not apply to a discharge of treated sewage from a certified on-board sewage treatment system installed on a vessel if:(a) the system is installed and maintained in accordance with Part 5B of the Marine Pollution Regulation 2001, and(b) the discharge occurs in navigable waters other than waters referred to in clause 22F (1) of that Regulation, and(c) at the time of the discharge, the vessel is being operated in accordance with any plan of management approved for the vessel under clause 22I of that Regulation.(2) In this clause, certified on-board sewage treatment system, and treated sewage have the same meanings as in Part 5B of the Marine Pollution Regulation 2001.cl 55A: Ins 27.6.2003.
56 Exemption from water pollution offence for pollutants arising from operation of engines propelling vessels
(1) Section 120 of the Act does not apply to the operation of an engine propelling a vessel.(2) The exemption arising under this clause does not apply:(a) if the engine is operated to dredge sediments, or(b) if the engine has been modified to discharge bilge water as it operates, or(c) if the engine has not been properly maintained so as to minimise pollution.
56A Exemption from water pollution offence in relation to cold water releases
Section 120 of the Act does not apply to the release of water that is more than 2 degrees Celsius colder than the water into which it is discharged if the water is released from a water supply work pursuant to an approval under the Water Management Act 2000 that contains one or more conditions relating to the work of a type specified in section 100 (3) of that Act.cl 56A: Ins 2005 No 118, Sch 3.
57 Emergency prohibition or regulation of aquatic activities—safety of drinking water
(1) The purpose of this clause is to enable the EPA to prohibit or regulate aquatic activities that threaten the safety of drinking water that is part of a public water supply in circumstances in which urgent action is required and other regulatory authorities are not authorised or have not acted to protect the safety of that drinking water.(2) For that purpose, the EPA may, by order published in the Gazette, prohibit or regulate specified aquatic activities in a specified area of water.(3) An order under this clause has effect for such period (not exceeding 3 months) as is specified in the order, unless the order is sooner revoked by a further order of the EPA published in the Gazette.(4) The EPA is to take such measures as it considers appropriate to bring a notice under this clause to the attention of the public, including publication of the notice in newspapers circulating in the area and notices erected near the area of water concerned.(5) A person who contravenes an order under this section is guilty of an offence.Maximum penalty: 5 penalty units.(6) In this section, aquatic activities include swimming, bathing, boating, waterskiing or fishing.
Chapter 3A National Pollutant Inventory
Part 3A.1 General
ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57A Object of Chapter
The object of this Chapter is to give effect to, and enforce compliance with, the National Environment Protection (National Pollutant Inventory) Measure made on 27 February 1998 under section 14 of the National Environment Protection Council Act 1994 of the Commonwealth.ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57B Interpretation
(1) In this Chapter:NPIM means the National Environment Protection (National Pollutant Inventory) Measure made on 27 February 1998 under section 14 of the National Environment Protection Council Act 1994 of the Commonwealth.occupier means an occupier, within the meaning of the NPIM, to whom this Chapter applies.reporting threshold for a substance means the reporting threshold for the substance specified in the NPIM.(2) The following words and expressions have the same meanings as they have in the NPIM:emission dataestimation techniquefacility (as defined in clause 3 (3) and modified in clause 9 (5) of the NPIM).industry handbookreporting facilityreporting periodsubstancesubstance identity informationsupporting datach 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57C Occupiers to whom this Chapter applies
This Chapter applies to an occupier of a reporting facility for whom an industry handbook:(a) has been agreed between the participating jurisdictions referred to in the NIPM, and(b) is published by the Commonwealth.ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
Part 3A.2 Reporting and record keeping requirements
ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57D Collection of data from reporting facilities
(1) Subject to Part 3A.4, the occupier of each facility is to provide the EPA with the following information if a reporting threshold for a substance is exceeded in a reporting period:(a) supporting data for the facility,(b) substance identity information and emission data, determined and documented in accordance with clause 57F, for each substance for which the reporting threshold is exceeded in the period,(c) any information that may be required to assess the integrity of the emission data,(d) a statement, signed by the occupier or a person authorised by the occupier for that purpose, that the occupier has exercised due diligence in gathering and providing the information referred to in paragraphs (a)–(c).(2) An occupier:(a) must provide the information referred to in subclause (1) to the EPA within 3 months after the end of the reporting period to which the information relates, and(b) must not provide any information to the EPA that is false or misleading in a material particular.Maximum penalty (subclause (2)): 40 penalty units (in the case of a corporation) or 20 penalty units (in the case of an individual).ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57E Occupier must keep data for period of 4 years
(1) The occupier of a reporting facility must keep the data used in deciding if the reporting threshold for a substance is exceeded in the reporting period for the occupier’s facility for 4 years after the reporting period ends.Maximum penalty: 40 penalty units (in the case of a corporation) or 20 penalty units (in the case of an individual).(2) The occupier must keep the data used in calculating emission data given to the EPA for 4 years after the emission data is required to be given.Maximum penalty: 40 penalty units (in the case of a corporation) or 20 penalty units (in the case of an individual).ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
Part 3A.3 Estimation techniques
ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57F Emission estimation techniques
In estimating emission data for the purposes of providing information under clause 57D, each occupier of a reporting facility must use one of the following estimation techniques:(a) the estimation technique set out in the industry handbook for the facility,(b) any of the methods provided in the load calculation protocol for the relevant activity issued by the EPA and in force, as referred to in clause 18 (2),(c) another estimation technique approved by the EPA for the facility under this Part.ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57G Application for approval of estimation technique
(1) The occupier of a facility may apply to the EPA for approval of an estimation technique for emission data.(2) The application must be in writing, setting out the technique for which approval is sought and giving the information necessary to enable the EPA to decide the application.(3) The EPA may, by written notice given to the occupier, ask the occupier to give to the EPA, in the reasonable period stated in the notice, further relevant information to enable the EPA to decide the application.ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57H Approving estimation technique
(1) The EPA may approve the estimation technique, or approve it subject to a modification decided by the EPA.(2) In deciding whether to approve the estimation technique, or approve it subject to a modification, the EPA must have regard to the accuracy of the technique compared with the accuracy of estimation techniques in the relevant industry handbook.(3) The EPA may refuse to approve the technique if the EPA has given the occupier a notice under clause 57G (3) asking for further information and the occupier does not comply with the request in the period stated in the notice.(4) Immediately after making a decision under this clause, the EPA must give the occupier written notice of the decision.(5) If the EPA decides to approve the technique subject to a modification, the notice must state the modification.(6) If the EPA refuses to approve the technique, or approves it subject to a modification, the notice must state that the approval is refused or given subject to a stated modification to the technique and the reasons for the refusal or modification.(7) Subclause (8) applies if the EPA fails to give the occupier a notice about the EPA’s decision on an application made by the occupier under clause 57G:(a) within 60 days after the application is made, or(b) if the occupier gave the EPA further information under clause 57G (3)—within 60 days after receiving the further information.(8) The EPA’s failure to give the notice is taken to be a decision by the EPA to refuse to approve the technique at the end of the relevant 60 days.ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
Part 3A.4 Exemptions from reporting requirements
ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57I Exemption on ground of national security
(1) This clause applies if the occupier of a facility gives the EPA written evidence that:(a) the occupier has made a claim to the Commonwealth under the NPIM that information required to be given by the occupier under clause 57D (2) (a) should be treated as confidential on the grounds of national security, and(b) the claim:(i) has been granted, or(ii) has not been assessed before the occupier is required to give the information to the EPA.(2) Subject to subclause (3), the occupier is exempted from giving the information to the EPA.(3) If the exemption is given by reason of a claim referred to in subclause (1) (b) (ii) and the Commonwealth refuses the claim after the occupier is required to give the information to the EPA, the occupier must give the information to the EPA within 60 days after receiving notice of the Commonwealth’s decision to refuse the claim.ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57J Claiming exemption on ground of commercial confidentiality
(1) The occupier of a facility may, by written notice given to the EPA, claim information required to be given by the occupier under clause 57D (2) (a) should be treated as confidential on the grounds of commercial confidentiality.(2) The notice must contain the information necessary to enable the EPA to decide the claim.(3) The EPA may, by written notice given to the occupier, ask the occupier to give the EPA, in the reasonable period stated in the notice, further relevant information to enable the EPA to decide the claim.ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
57K Deciding claim for exemption on ground of commercial confidentiality
(1) The EPA may grant the claim only if the EPA reasonably believes that a document referring to the information would be an exempt document under clause 7 or 8 of Schedule 1 to the Freedom of Information Act 1989.(2) If the EPA grants the claim, the occupier is exempted from giving the information to the EPA.(3) The EPA may refuse to grant the claim if the EPA has given the occupier a notice under clause 57J (3) asking for further information and the occupier does not comply with the request in the period stated in the notice.(4) The EPA must give the occupier written notice of the EPA’s decision on the claim.(5) If the EPA refuses to grant the claim, the notice must state that the claim is refused and the reasons for the refusal.(6) Subclause (7) applies if the EPA fails to give the occupier a notice about the EPA’s decision on the claim:(a) within 60 days after the claim is made, or(b) if the occupier gave the EPA further information under clause 57J (3)—within 60 days after receiving the further information.(7) The EPA’s failure to give the notice is taken to be a decision by the EPA to refuse to grant the claim at the end of the relevant 60 days.ch 3A, Parts 3A.1–3A.4 (cll 57A–57K): Ins 17.5.2002.
Chapter 3B Burning of bio-material in electricity generating works
ch 3B (cll 57L–57R): Ins 10.1.2003.
57L Definitions
In this Chapter:Australian native tree means any tree of a species indigenous to Australia.electricity generating work means a work (including associated facilities) that supplies, or is capable of supplying, more than 200 kilowatts of electricity.EPA guidelines means guidelines in force under section 57Q.forest bio-material means the bio-material comprised in trees.native forest bio-material means the bio-material comprised in Australian native trees, other than:(a) bio-material obtained from:(i) an authorised plantation within the meaning of the Plantations and Reafforestation Act 1999, or(ii) an existing plantation within the meaning of section 9 of the Plantations and Reafforestation Act 1999, or(iii) land on which exempt farm forestry (within the meaning of the Plantations and Reafforestation Act 1999) is being carried out, or(iv) land on which ancillary plantation operations (within the meaning of section 9 of the Plantations and Reafforestation Act 1999) are being carried out, or(b) sawdust or other sawmill waste, or(c) waste arising from wood processing or the manufacture of wooden products, other than waste arising from activities (such as woodchipping or the manufacture of railway sleepers) carried out at the location from which the Australian native trees are harvested.ch 3B (cll 57L–57R): Ins 10.1.2003.
57M Native forest bio-material not to be used for electricity generation
The occupier of any premises who causes or allows native forest bio-material to be burned in any electricity generating work in or on those premises is guilty of an offence.Maximum penalty:(a) in the case of a corporation—400 penalty units,(b) in the case of an individual—200 penalty units.ch 3B (cll 57L–57R): Ins 10.1.2003.
57N Record-keeping
(1) The occupier of any premises who causes or allows bio-material of any kind to be burned in any electricity generating work in or on those premises during a reporting period must keep records, as required by the EPA guidelines, in relation to fuel held during that period at those premises.(2) Within 60 days after the end of each reporting period, the occupier:(a) must prepare reports to be prepared, as required by the EPA guidelines, in relation to:(i) the use of the electricity generating work, andduring that period, and(ii) the use of forest bio-material as fuel for the electricity generating work,(b) must cause any such report to be audited by an auditor having the qualifications set out in the EPA guidelines, and(c) must send a copy of any such report, certified in accordance with the EPA guidelines, to the EPA.(3) The occupier must retain all records kept under this clause for at least 4 years after the end of the reporting period to which they relate.(4) The occupier is guilty of an offence if the requirements of this clause are not complied with.Maximum penalty:(a) in the case of a corporation—200 penalty units,(b) in the case of an individual—100 penalty units.(5) This clause does not apply to an electricity generating plant in relation to any reporting period that commenced before 1 July 2003.(6) In this clause, reporting period, in relation to an electricity generating work, means:(a) in the case of a work the subject of an environment protection licence, the licence fee period in relation to that licence (within the meaning of Part 2.1), or(b) in the case of any other work, the year ending 30 June.ch 3B (cll 57L–57R): Ins 10.1.2003.
57O Reports to be made publicly available
The EPA is to ensure that the reports sent to it under this Chapter are made available at its head office for inspection by members of the public.ch 3B (cll 57L–57R): Ins 10.1.2003.
57P Offence of providing false information
(1) A person who, in or in connection with a requirement under this Chapter, provides any information, or makes any statement, that is false or misleading in a material particular is guilty of an offence.Maximum penalty:(a) in the case of a corporation—200 penalty units,(b) in the case of an individual—100 penalty units.(2) It is a defence to a prosecution for an offence against this clause if the person establishes that the person had reasonable grounds to believe that the information or statement was true and had no reason to suspect that the information or statement was false or misleading in a material respect.ch 3B (cll 57L–57R): Ins 10.1.2003.
57Q EPA guidelines
The EPA may, by order published in the Gazette, establish guidelines as to the keeping of records, and the preparation and auditing of reports, for the purposes of this Chapter.ch 3B (cll 57L–57R): Ins 10.1.2003.
57R Appropriate regulatory authority
Pursuant to section 6 (3) of the Act, the EPA is declared to be the appropriate regulatory authority for any matter arising under this Chapter.Note—As a consequence of this declaration, a local authority is not the appropriate regulatory authority for any such matter for which (but for this clause) it would be the appropriate regulatory authority under section 6 (2) of the Act.ch 3B (cll 57L–57R): Ins 10.1.2003.
Chapter 3C Land pollution
ch 3C: Ins 2006 (217), Sch 1 [1].
57S Meaning of certain expressions
For the purposes of section 142D of the Act:manure, virgin excavated natural material and biosolids have the same meanings as they have in Division 2 of Part 3 of Schedule 1 to the Act.non-hazardous agricultural or crop waste means agricultural or crop waste that is not hazardous waste or restricted solid waste within the meaning of Schedule 1 to the Act.cl 57S: Ins 2006 (217), Sch 1 [1]. Am 2008 (109), Sch 2 [6].
Chapter 3D Green offsets
ch 3D (cl 57T): Ins 2006 (217), Sch 1 [1].
57T Evaluation of green offset schemes or works
(1) Each green offset scheme, and each green offset work that is not part of a green offset scheme, must be evaluated in accordance with this clause.(2) An evaluation is to be carried out and reported on:(a) in the case of a green offset scheme—at the intervals (not being greater than 5 years) determined by the EPA for the duration of the scheme and at the end of the scheme, and(b) in the case of a green offset work that is not part of a green offset scheme—at the intervals determined by the EPA in respect of the work.(3) An evaluation is to be carried out and reported on by the EPA or by a manager of a green offset scheme or green offset work if directed to do so in accordance with subclause (4).(4) The EPA may, by notice in writing given to the manager of a green offset scheme or green offset work, direct that the manager do any of the following:(a) provide the EPA with information relating to the effectiveness of the scheme or work,(b) carry out and report on an evaluation required under this clause and provide a copy of the evaluation report to the EPA,(c) amend any such evaluation report.(5) An evaluation report:(a) must list the participants in the green offset scheme or green offset work, and(b) must relate to the period since the commencement of the scheme or work or, if the scheme or work has been evaluated under this clause, since the last evaluation of the scheme or work, and(c) must set out the environmental effects and benefits arising from the scheme or work, and(d) in the case of a scheme, must contain any of the following matters that are relevant to the scheme:(i) whether any applicable cap or target has been met,(ii) particulars of the costs of and payments for the purposes of the scheme under Part 9.3B of the Act,(iii) particulars of the implementation of any works for the purposes of the scheme, and(e) in the case of a work that is not part of a scheme, must contain any of the following matters that are relevant to the work:(i) particulars of the implementation of the work by or on behalf of the participants,(ii) particulars of the costs of and payments for the purposes of the work under Part 9.3B of the Act, and(f) must contain any other matters directed to be included by the EPA, and(g) must be made publicly available in the manner determined by the EPA.(6) Nothing in this clause requires or permits the EPA or the manager of a green offset scheme or green offset work to make publicly available any information of a kind referred to in section 319 (1) of the Act.ch 3D (cl 57T): Ins 2006 (217), Sch 1 [1].
Chapter 4 General provisions
Part 4.1 Police entry powers regarding noise
58 Warrants relating to noise abatement directions
(1) For the purposes of section 280 (5) of the Act, the prescribed form of record to be made by a Magistrate when a warrant is granted is Form 1 in Schedule 4.(2) For the purposes of section 280 (10) of the Act, the prescribed form of record to be made by a police officer when a warrant is granted is Form 2 in Schedule 4.(3) For the purposes of section 280 (11) (a) of the Act, the prescribed statement to be furnished to a resident of premises entered pursuant to a warrant is Form 3 in Schedule 4.
Part 4.2 Appeals
59 Appeals regarding noise: sec 290
For the purposes of section 290 of the Act, the period within which a person may appeal to the Land and Environment Court against a noise control notice relating to the keeping of an animal at premises is 7 days (instead of 21 days) after service of the notice.
Part 4.3 Fees relating to environment protection notices and noise control notices
pt 4.3, hdg: Am 2006 (217), Sch 1 [2].
60 Fee for administrative costs of preparing and giving clean-up notice: sec 94 (2)
The fee payable under section 94 (2) of the Act to a regulatory authority by a person who is given a clean-up notice by that authority is $320.Note—Section 94 of the Act provides that the fee is payable within 30 days. Application may be made under that section to the authority for an extension of time to pay the fee or for the waiving of payment of the fee. A failure to pay the fee within the requisite time constitutes an offence.
61 Fee for administrative costs of preparing and giving prevention notice: sec 100 (2)
The fee payable under section 100 (2) of the Act to a regulatory authority by a person who is given a prevention notice by that authority is $320.Note—Section 100 of the Act provides that the fee is payable within 30 days (subject to appeal proceedings). Application may be made under that section to the authority for an extension of time to pay the fee or for the waiving of payment of the fee. A failure to pay the fee within the requisite time constitutes an offence.
61A Fee for administrative costs of preparing and giving noise control notice
The fee payable under section 267A (2) of the Act to a regulatory authority by a person who is given a noise control notice is $320.Note—Section 267A of the Act provides that the fee is payable within 30 days (subject to appeal proceedings). Application may be made under that section to the authority for an extension of time to pay the fee or for the waiving of payment of the fee. A failure to pay the fee within the requisite time constitutes an offence.cl 61A: Ins 2006 (217), Sch 1 [3].
Part 4.4 Financial assurances
62 Additional restriction on requiring financial assurances: sec 299 (d)
The following matter is prescribed for the purposes of section 299 (d) of the Act:The adequacy of financial assurances (if any) already provided, or required to be provided, by the same person to a public authority to secure or guarantee funding for or towards the carrying out of the same or substantially the same works or programs for which a financial assurance is contemplated under the Act.Note—Section 299 of the Act prevents a regulatory authority from imposing a condition on a licence requiring a financial assurance to be provided unless it is satisfied that the condition is justified having regard to a number of specified matters. The above clause specifies additional matters to which the authority must have regard for that purpose.
Part 4.5 Public register
63 Additional matters to be included in public register: sec 308
(1) Details of the following additional matters must be recorded in the public register kept by a regulatory authority under section 308 of the Act:(a) the application fee for an environment protection licence issued by that authority,(b) the annual licence fee paid or payable in respect of an environment protection licence issued by that authority,(c) any approval granted under clause 6G or 31 of the Protection of the Environment Operations (Clean Air) Regulation 2002,(d) (Repealed)(e) any information relating to actual load, agreed load or weighted load of an assessable pollutant reported by a licensee in an annual return to the appropriate regulatory authority,(f) details or summaries of undertakings given under section 253A of the Act,(g) details or summaries of load reduction agreements entered into in accordance with clause 25.(2) In this clause actual load, agreed load and weighted load have the same meaning as in Part 2.1.cl 63: Am 25.8.2000; 17.8.2001; 2005 No 96, Sch 2.3 [3]; 2006 (491), Sch 2.
Part 4.6 Appropriate regulatory authority
pt 4.6: Ins 25.6.1999.
64 Marine Parks Authority
(1) The Marine Parks Authority is declared, under section 6 (3) of the Act, to be the appropriate regulatory authority for non-scheduled activities in marine parks, except in relation to the following:(a) the exercise of functions under Chapter 3 of the Act,(b) premises defined in an environment protection licence as the premises to which the licence applies, and all activities carried on at those premises,(c) activities carried on by the State or a public authority, whether at premises occupied by the State or a public authority or otherwise,(d) a matter for which a public authority (other than a local authority or the Marine Parks Authority) is declared under section 6 (3) of the Act to be the appropriate regulatory authority.(2) In this clause:marine park means a marine park within the meaning of the Marine Parks Act 1997, but does not include any part of a marine park:(a) that is on the landward side of the mean high water mark of the waters within the marine park, and(b) that is within a local government area under the Local Government Act 1993.Marine Parks Authority means the Marine Parks Authority constituted under the Marine Parks Act 1997.cl 64: Ins 25.6.1999. Am 7.12.2001.
64A Waterways Authority
(1) The Waterways Authority is declared, under section 6 (3) of the Act, to be the appropriate regulatory authority for non-scheduled activities involving a non-pilotage vessel in navigable waters, except in relation to the following:(a) the exercise of functions under Chapter 3 of the Act,(b) premises defined in an environment protection licence as the premises to which the licence applies, and all activities carried on at those premises,(c) activities carried on by the State or a public authority, whether at premises occupied by the State or a public authority or otherwise,(d) a matter for which a public authority (other than a local authority or the Waterways Authority) is declared under section 6 (3) of the Act to be the appropriate regulatory authority,(e) non-scheduled activities in marine parks (within the meaning of clause 64).(2) For the purposes of this clause:non-pilotage vessel means any vessel other than:(a) a vessel for which pilotage is compulsory under Part 6 of the Ports Corporatisation and Waterways Management Act 1995 in any port, and(b) a vessel for which pilotage would be compulsory under Part 6 of the Ports Corporatisation and Waterways Management Act 1995 in any port if the master did not hold a pilotage exemption certificate.cl 64A: Ins 7.12.2001.
64B Director-General of National Parks and Wildlife
The Director-General of National Parks and Wildlife is declared, under section 6 (3) of the Act, to be the appropriate regulatory authority for non-scheduled activities in Kosciuszko National Park, except in relation to the following:(a) the exercise of functions under Chapter 3 of the Act,(b) premises defined in an environment protection licence as the premises to which the licence applies, and all activities carried on at those premises,(c) activities carried on by the State or a public authority, whether at premises occupied by the State or a public authority or otherwise,(d) a matter for which a public authority (other than a local authority or the Director-General of National Parks and Wildlife) is declared under section 6 (3) of the Act to be the appropriate regulatory authority,(e) non-scheduled activities involving a non-pilotage vessel (within the meaning of clause 64A) in navigable waters.cl 64B: Ins 1.8.2003.
65 SOCOG
(1) The EPA is declared, under section 6 (3) of the Act, to be the appropriate regulatory authority for premises occupied by, or activities carried on by, SOCOG.(2) For the purposes of this clause, premises occupied by SOCOG include premises at which Olympic events are being conducted, and activities carried on by SOCOG include Olympic events.(3) In this clause:Olympic event means:(a) an event in the Sydney 2000 Olympic Games, or(b) an event that SOCOG declares to be a test event for the Sydney 2000 Olympic Games.SOCOG means the Sydney Organising Committee for the Olympic Games constituted by the Sydney Organising Committee for the Olympic Games Act 1993.cl 65: Ins 25.6.1999.
66 Inner West Light Rail
(1) The EPA is declared, under section 6 (3) of the Act, to be the appropriate regulatory authority for non-scheduled activities on the route of the light rail system declared under section 104N (2) of the Transport Administration Act 1988 (as declared by clauses 11, 12 and 14 of the Transport Administration (General) Regulation 2000).(2) This clause does not apply to buildings or other structures that are taken to be included in the route of the light rail system by clause 13 (1) (b) of the Transport Administration (General) Regulation 2000.cll 66: Ins 30.3.2001.
67 Outdoor entertainment activities
(1) The EPA is declared, under section 6 (3) of the Act, to be the appropriate regulatory authority for outdoor entertainment activities carried on at any of the following premises:(a) the Trust lands within the meaning of the Royal Botanic Gardens and Domain Trust Act 1980,(b) the Trust lands within the meaning of the Centennial Park and Moore Park Trust Act 1983,(c) the Darling Harbour area within the meaning of the Sydney Harbour Foreshore Authority Regulation 1999,(d) the trust land within the meaning of Parramatta Stadium Trust Act 1988,(e) the trust lands within the meaning of Sydney Cricket and Sports Ground Act 1978,(f) Homebush Bay within the meaning of the Homebush Bay Operations Act 1999,(g) the Opera House premises within the meaning of the Opera House Trust By-law 1998.(2) In this clause, outdoor entertainment activities means any of the following activities, but only if the activity is carried on outdoors and sound amplification equipment is used as part of the activity:(a) concerts,(b) festivals,(c) cinematic and theatrical events,and includes any rehearsals, sound checks or other preparations for the activities listed in paragraphs (a) to (d).(d) sporting events,(3) Despite subclause (1), the EPA is not the appropriate regulatory authority for outdoor entertainment activities involving less than 200 persons.(4) In this clause, a reference to an activity being carried on outdoors includes an activity being carried on under or within a tent, marquee or similar structure.cll 67: Ins 30.3.2001.
67A Underground petroleum storage systems
The EPA is declared, under section 6 (3) of the Act, to be the appropriate regulatory authority for any matter arising under the Protection of the Environment Operations (Underground Petroleum Storage Systems) Regulation 2008.cl 67A: Ins 2008 (81), Sch 1.1 [1].
67B Existing waste activities
The EPA is declared, under section 6 (3) of the Act, to be the appropriate regulatory authority for any non-scheduled activity that, immediately before 28 April 2008 (the commencement of the Protection of the Environment Operations Amendment (Scheduled Activities and Waste) Regulation 2008), was licensed as a waste activity (within the meaning of Schedule 1 to the Act, as then in force) but only for so long as that waste activity continues.cl 67B: Ins 2008 (109), Sch 2 [7].
Part 4.7 Exceptions
pt 4.7: Ins 30.3.2001.
68 Exception from prohibition on placing advertising material on vehicles: section 146B (3) (b)
(1) Section 146B of the Act does not apply to the deposit in or on a motor vehicle of the following material:(a) community safety and crime prevention brochures deposited by or on behalf of the Police Service,(b) brochures, relating to the issue of mobility parking scheme authorities, deposited by or on behalf of the Roads and Traffic Authority.(2) In this clause, has the same meaning as in the Road Transport (Safety and Traffic Management) Regulation 1999.cl 68: Ins 30.3.2001. Am 2008 (189), Sch 1.6.
69 Exemption for noise control and abatement provisions
(1) Activities carried out at the Luna Park site are exempt from the following provisions of the Act:(a) Part 4.3 of Chapter 4 (but only insofar as the provisions relate to the emission of noise),(b) section 139,(c) Part 8.6 of Chapter 8.(2) Subclause (1) applies only if the activities carried out at the Luna Park site are subject to one or more of the following development consents and are carried out in compliance with such of the conditions of those consents as are relevant to those activities:(a) the consent to development application 154–06–01 granted by the Minister on 31 January 2002 under section 80 of the Environmental Planning and Assessment Act 1979,(b) the consent to development application 151–5–2002 granted by the Minister on 21 January 2003 under section 80 of the Environmental Planning and Assessment Act 1979,(c) the consent to development application 201–6–2002 granted by the Minister on 21 January 2003 under section 80 of the Environmental Planning and Assessment Act 1979.(3) In this clause:development application has the same meaning as in the Environmental Planning and Assessment Act 1979.Luna Park site has the same meaning as in the Luna Park Site Act 1990.Minister, in relation to a consent to a development application, means the Minister who was consent authority for the development concerned under clause 10 of the State Environmental Planning Policy No 56—Sydney Harbour Foreshores and Tributaries.cl 69: Ins 11.3.2005.
Part 4.8 Vehicle testing and inspection
Division 1 Preliminary
pt 4.8, div 1: Ins 2007 (123), Sch 1.
70 Definitions
In this Part:approved inspection station means premises approved under clause 73.approved mechanic means an individual approved under clause 72.proprietor, in relation to premises, means a person who:(a) carries on or proposes to carry on a business at the premises, or(b) is the occupier of the premises.vehicle inspection report means a vehicle inspection report referred to in clause 75.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
71 Application of Part
This Part applies in relation to the testing or inspection of motor vehicles required to be carried out in accordance with a notice given for the purposes of section 207 (2) (c) of the Act.Note—Section 207 of the Act provides that an authorised officer may issue a notice requiring articles (which include motor vehicles) to be tested or inspected for the purpose of determining whether the article complies with the requirements of the Act or regulations made under the Act. Under section 207 (2) (c) of the Act, such a notice may require a motor vehicle to be tested or inspected at a place approved by the EPA by a person approved by the EPA.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
Division 2 Approved mechanics and approved inspection stations
pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
72 Approved mechanics
(1) An individual may apply to the EPA for an approval to carry out tests or inspections to which this Part applies.(2) An application under this clause must:(a) be made in the manner and form approved by the EPA, and(b) be supported by any information required by the EPA.(3) The EPA may, if it considers it necessary in order to determine the suitability of the applicant for an approval under this clause, require the applicant to furnish to the EPA, within a specified time, any further particulars that the EPA considers necessary.(4) The EPA is to determine an application under this clause by granting or refusing to grant the application.(5) The EPA may refuse to grant the application if, in its opinion, the individual is not a fit and proper person to carry out tests or inspections to which this Part applies.(6) The EPA must give notice in writing of the determination of the application under this clause to the applicant, including, if the application is granted, notice of the date from which the approval takes effect and any conditions to which the approval is subject.(7) An approval under this clause:(a) applies to the testing or inspection of motor vehicles generally or to the class or classes of vehicles specified in the approval, and(b) remains in force until it is surrendered, suspended or revoked, and(c) is to be given in the manner and in the form approved by the EPA, and(d) may be given unconditionally or subject to such conditions as the EPA considers appropriate.(8) A person must not hold himself or herself out as a person authorised to carry out tests or inspections to which this Part applies, or issue a vehicle inspection report in relation to any such test or inspection, unless the person is an approved mechanic.Maximum penalty:(a) in the case of a corporation—200 penalty units, or(b) in the case of an individual—100 penalty units.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
73 Approved inspection stations
(1) A proprietor of premises may apply to the EPA for an approval of the premises to be used for the purpose of carrying out tests or inspections to which this Part applies.(2) An application under this clause must:(a) be made in the manner and form approved by the EPA, and(b) be supported by any information required by the EPA.(3) The EPA may, if it considers it necessary in order to determine the suitability of the applicant for an approval under this clause, require the applicant to furnish to the EPA, within a specified time, any further particulars that the EPA considers necessary.(4) The EPA is to determine an application under this clause by granting or refusing to grant the application.(5) The EPA may refuse to grant the application:(a) if, in its opinion, the premises the subject of the application or the equipment on the premises are not suitable for the purpose of carrying out tests or inspections to which this Part applies, or(b) if, in its opinion, the applicant is not a fit and proper person to carry out the responsibilities associated with using the premises for that purpose, or(c) for any other reason the EPA considers appropriate.(6) The EPA must give notice in writing of the determination of the application for an approval under this clause to the applicant, including, if the application is granted, notice of the date from which the approval takes effect and any conditions to which the approval is subject.(7) An approval under this clause:(a) applies to the testing or inspection of motor vehicles generally or to the class or classes of vehicles specified in the approval, and(b) remains in force until it is surrendered, suspended or revoked, and(c) is to be given in the manner and in the form approved by the EPA, and(d) may be given unconditionally or subject to such conditions as the EPA considers appropriate.(8) A proprietor of premises must not allow the premises to be used for the purpose of carrying out a test or inspection to which this Part applies unless:(a) the premises are an approved inspection station, and(b) the test or inspection of the vehicle is a test or inspection of a vehicle to which the approval applies, and(c) the test or inspection is carried out by an approved mechanic.Maximum penalty (subclause (8)):(a) in the case of a corporation—200 penalty units, or(b) in the case of an individual—100 penalty units.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
74 Maximum fee for test or inspection
The maximum fee that may be charged for the carrying out of a test or inspection to which this Part applies is:(a) in the case of a motorcycle—$40.15, or(b) in any other case—$60.50.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
75 Vehicle inspection reports
(1) An approved mechanic who carries out a test or inspection to which this Part applies must, in accordance with conditions of the mechanic’s approval, complete a vehicle inspection report in the form approved by the EPA.(2) Copies of a completed vehicle inspection report must be given to:(a) the owner of the relevant motor vehicle or a person acting on behalf of the owner, andin accordance with the conditions of an approval under clause 72 or 73, as the case may be.(b) the EPA,(3) A person must not issue a vehicle inspection report in relation to a test or inspection to which this Part applies if the person knows, or ought reasonably to suspect, that the report is false or misleading in a material particular.Maximum penalty:(a) in the case of a corporation—200 penalty units, or(b) in the case of an individual—100 penalty units.(4) The holder of an approval for an approved inspection station who allows a vehicle inspection report to be issued in relation to a test or inspection to which this Part applies that is carried out at the station is guilty of an offence if the person knows, or ought reasonably to suspect, that the report is false or misleading in a material particular.Maximum penalty (subclause (4)):(a) in the case of a corporation—200 penalty units, or(b) in the case of an individual—100 penalty units.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
76 Variation of approvals under this Part
(1) The EPA may, by notice in writing, vary an approval given under this Part (including the conditions of an approval).(2) A variation includes the attaching of a condition to an approval (whether or not any conditions have already been attached), the substitution of a condition, the omission of a condition or the amendment of a condition.(3) An approval may be varied on application in writing to the EPA by the holder of the approval or on the initiative of the EPA.(4) An approval may be varied at any time during its currency.(5) A variation operates from the date of the EPA’s decision to grant or issue the variation or another date specified by the EPA in the notice.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
77 Surrender of approvals under this Part
(1) The holder of an approval under this Part may surrender the approval by giving notice in writing to the EPA.(2) The surrender of an approval under this clause does not take effect until 28 days, or some other period approved by the EPA, after the notice has been given to the EPA.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
78 Suspension or revocation of approvals under this Part
(1) The EPA may, by notice in writing, suspend or revoke an approval under this Part if:(a) the holder has contravened a provision of this Part, or(b) the holder or the premises concerned no longer satisfies the relevant requirements for approval under this Part, or(c) the holder has failed to comply with a condition to which the approval is subject, or(d) the holder provided false or misleading information in the application for approval, or(e) the EPA is, for any reason, of the opinion that the holder is not a fit and proper person to continue to hold the approval.(2) A suspension of an approval under this clause may be for a specified period or until further notice in writing by the EPA.(3) A suspension or revocation of an approval under this clause operates from the day the notice of the suspension or revocation is given to the holder of the approval or from such later day as the notice specifies.(4) The EPA must not suspend or revoke an approval unless before doing so:(a) it has given notice to the holder of the approval that it intends to do so, and(b) it has specified in that notice the reasons for its intention to do so, and(c) it has given the holder a reasonable opportunity to make submissions in relation to the proposed suspension or revocation, and(d) it has taken into consideration any such submissions by the holder.(5) An approval may be revoked under this clause during the currency of a suspension.pt 4.8, div 2 (cll 70–78): Ins 2007 (123), Sch 1.
Part 4.9 Savings and transitional provisions
pt 4.9 (cll 79–82): Ins 2008 (109), Sch 2 [8].
79 Definitions
In this Part:existing licence means a licence that was in force immediately before 28 April 2008, but does not include a licence for an activity that has ceased to be a scheduled activity as a consequence of the commencement of the 2008 amending Regulation unless the licence:(a) has, under the new rules, become a licence for a different kind of scheduled activity, or(b) continues to authorise the pollution of water for the purposes of section 122 of the Act.the 2008 amending Regulation means the Protection of the Environment Operations Amendment (Scheduled Activities and Waste) Regulation 2008.the new rules means Schedule 1 to the Act, as amended by the 2008 amending Regulation, and Schedule 1 to this Regulation, as so amended.the old rules means Schedule 1 to the Act, as in force immediately before 28 April 2008, and Schedule 1 to this Regulation, as then in force.pt 4.9 (cll 79–82): Ins 2008 (109), Sch 2 [8].
80 Pending applications
(1) The new rules apply to and in respect of a pending application.(2) In this clause, pending application means an application for a licence that had been made, but not determined, before 28 April 2008.pt 4.9 (cll 79–82): Ins 2008 (109), Sch 2 [8].
81 Existing licences
(1) Subject to this clause, the old rules continue to apply to and in respect of an existing licence as if the 2008 amending Regulation had not been made.(2) The EPA may, for the purposes of this Part, replace an existing licence with a new licence, whether with or without variation.(3) A new licence takes effect, and the existing licence it replaces ceases to have effect, when notice of that fact (whether or not accompanied by a copy of the new licence) is served on the licensee.(4) To the extent to which the authority conferred by the new licence differs from the authority conferred by the existing licence it replaces, the existing licence is taken to be varied under section 58 of the Act and the Act applies accordingly.Note—Section 287 of the Act provides for appeals against variations of a licence.(5) This clause does not limit the power of the EPA to vary an existing licence under the Act.pt 4.9 (cll 79–82): Ins 2008 (109), Sch 2 [8].
82 Changes of classification
(1) Subject to subclause (2), clause 34 applies to any change in:(a) the classification of any activity, andbeing a change that arises from the replacement of the old rules by the new rules as if the change arose from a change in the activity itself.(b) the fees payable in respect of any activity,(2) Clause 34 (2) does not apply in relation to any change referred to in subclause (1).(3) For the purposes of clause 34, as applied by subclause (1):(a) any such change is taken to have occurred, in relation to any activity for which a licence was in force immediately before 28 April 2008:(i) at the end of the licence fee period during which that date occurred, orwhichever is the later, and(ii) when the licence is replaced by a new licence,(b) if any such change is taken to have occurred at the end of the licence fee period during which 28 April 2008 occurred, the fact that the licence is replaced by a new licence before the end of that period is to be ignored.(4) For the purposes of this clause, any statement that is of the kind referred to in clause 6 (4), as in force immediately before 28 April 2008, and that was included in Schedule 1 to this Regulation, as then in force, is of no effect.pt 4.9 (cll 79–82): Ins 2008 (109), Sch 2 [8].
Schedule 1 Licensing fees
(Clauses 6, 9, 10, 12, 13, 17, 22, 33 and 43A)
AGRICULTURAL PROCESSING | ||
Dairy processing (see clause 2 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: megalitres | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 30,000 megalitres | 5 | |
More than 30,000 but not more than 100,000 megalitres | 15 | |
More than 100,000 megalitres | 50 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
General agricultural processing (see clause 2 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 but not more than 100,000 tonnes | 15 | |
More than 100,000 but not more than 250,000 tonnes | 50 | |
More than 250,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Grape processing (see clause 2 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 but not more than 100,000 tonnes | 15 | |
More than 100,000 but not more than 250,000 tonnes | 50 | |
More than 250,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
AQUACULTURE AND MARICULTURE | ||
Aquaculture and mariculture (see clause 3 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: megalitres | |
2 | Administrative fee | |
Annual volume of discharge | Administrative fee units | |
Not more than 2,000 megalitres | 5 | |
More than 2,000 but not more than 20,000 megalitres | 15 | |
More than 20,000 megalitres | 50 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
BITUMEN MIXING | ||
Bitumen mixing (see clause 4 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 30,000 tonnes | 15 | |
More than 30,000 but not more than 100,000 tonnes | 50 | |
More than 100,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
BREWING AND DISTILLING | ||
Brewing and distilling (see clause 5 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 5 | |
More than 10,000 but not more than 20,000 tonnes | 50 | |
More than 20,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
CEMENT OR LIME WORKS | ||
Cement or lime handling (see clause 6 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual handling capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 but not more than 100,000 tonnes | 8 | |
More than 100,000 but not more than 500,000 tonnes | 25 | |
More than 500,000 but not more than 2,000,000 tonnes | 65 | |
More than 2,000,000 tonnes | 165 | |
3 | Load-based fee (but only if the annual handling capacity exceeds 30,000 tonnes) | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.23 | |
Fine particulates | 0.37 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Cement or lime production (see clause 6 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 but not more than 100,000 tonnes | 65 | |
More than 100,000 but not more than 250,000 tonnes | 165 | |
More than 250,000 but not more than 500,000 tonnes | 300 | |
More than 500,000 tonnes | 420 | |
3 | Load-based fee (but only if the annual production capacity exceeds 30,000 tonnes) | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.23 | |
Fine particulates | 0.37 | |
Nitrogen oxides and nitrogen oxides (summer) | 3.2 | |
Sulfur oxides | 0.16 | |
Water pollutants | Threshold factor | |
Nil | Not applicable |
CERAMIC WORKS | ||
Ceramic waste generation (see clause 7 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee (but only if the activity is a scheduled activity under clause 7 (2) of Schedule 1 to the Act) | |
Annual volume of waste generated or stored | Administrative fee units | |
More than 5 but not more than 100 tonnes | 8 | |
More than 100 tonnes | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Ceramics production (see clause 7 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 15,000 tonnes | 8 | |
More than 15,000 but not more than 50,000 tonnes | 25 | |
More than 50,000 but not more than 200,000 tonnes | 65 | |
More than 200,000 tonnes | 165 | |
3 | Load-based fee (but only if the annual production capacity exceeds 15,000 tonnes) | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.18 | |
Fine particulates | 1.58 | |
Fluoride | 0.8 | |
Nitrogen oxides and nitrogen oxides (summer) | 10.5 | |
Sulfur oxides | 18.2 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Glass production (see clause 7 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual melting capacity | Administrative fee units | |
Not more than 15,000 tonnes | 8 | |
More than 15,000 but not more than 30,000 tonnes | 25 | |
More than 30,000 but not more than 100,000 tonnes | 65 | |
More than 100,000 tonnes | 165 | |
3 | Load-based fee (but only if the annual melting capacity exceeds 15,000 tonnes) | |
Production of container glass | ||
Air pollutants | Threshold factor | |
Coarse particulates | 0.05 | |
Fine particulates | 0.05 | |
Nitrogen oxides and nitrogen oxides (summer) | 4.02 | |
Sulfur oxides | 3.12 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Production of float glass | ||
Air pollutants | Threshold factor | |
Coarse particulates | 0.11 | |
Fine particulates | 0.11 | |
Nitrogen oxides and nitrogen oxides (summer) | 2.00 | |
Sulfur oxides | 3.64 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Production of other glass | ||
Air pollutants | Threshold factor | |
Coarse particulates | 2.75 | |
Fine particulates | 2.75 | |
Nitrogen oxides and nitrogen oxides (summer) | 4.29 | |
Sulfur oxides | 4.16 | |
Water pollutants | Threshold factor | |
Nil | Not applicable |
CHEMICAL PRODUCTION | ||
Agricultural fertiliser (inorganic) production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 50,000 tonnes | 25 | |
More than 50,000 but not more than 100,000 tonnes | 65 | |
More than 100,000 tonnes | 165 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Agricultural fertiliser (phosphate) production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 50,000 tonnes | 25 | |
More than 50,000 but not more than 100,000 tonnes | 65 | |
More than 100,000 tonnes | 165 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 8 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.022 | |
Fine particulates | 0.13 | |
Fluoride | 1.1 | |
Water pollutants | Threshold factor | |
Total phosphorous | 0.002 | |
Ammonium nitrate production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 50,000 tonnes | 25 | |
More than 50,000 but not more than 100,000 tonnes | 65 | |
More than 100,000 tonnes | 165 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 8 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.77 | |
Fine particulates | 0.33 | |
Nitrogen oxides and nitrogen oxides (summer) | 1.5 | |
Water pollutants | Threshold factor | |
Total nitrogen | 0.11 | |
Battery production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 500 tonnes | 15 | |
More than 500 but not more than 1,500 tonnes | 50 | |
More than 1,500 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Chemical production waste generation (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee (but only if the activity is a scheduled activity under clause 8 (2) of Schedule 1 to the Act) | |
Annual volume of waste generated or stored | Administrative fee units | |
More than 5 but not more than 100 tonnes | 8 | |
More than 100 tonnes | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Dangerous goods production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 15 | |
More than 10,000 but not more than 25,000 tonnes | 50 | |
More than 25,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Explosives production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 2,000 tonnes | 15 | |
More than 2,000 but not more than 10,000 tonnes | 50 | |
More than 10,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Paints/polishes/adhesives production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 5,000 tonnes | 25 | |
More than 5,000 but not more than 15,000 tonnes | 65 | |
More than 15,000 tonnes | 165 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 8 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Benzene | 0.27 | |
Fine particulates | 5.0 | |
Nitrogen oxides and nitrogen oxides (summer) | 3.0 | |
VOCs and VOCs (summer) | 8.73 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Pesticides and related products production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 2,000 tonnes | 15 | |
More than 2,000 but not more than 10,000 tonnes | 50 | |
More than 10,000 but not more than 30,000 tonnes | 135 | |
More than 30,000 tonnes | 335 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Pesticides and related products (toxic substances) production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 2,000 tonnes | 15 | |
More than 2,000 but not more than 10,000 tonnes | 50 | |
More than 10,000 but not more than 30,000 tonnes | 135 | |
More than 30,000 tonnes | 335 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Petrochemical production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 25 | |
More than 10,000 but not more than 30,000 tonnes | 65 | |
More than 30,000 but not more than 100,000 tonnes | 165 | |
More than 100,000 but not more than 200,000 tonnes | 300 | |
More than 200,000 tonnes | 420 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 8 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Benzene | 0.25 | |
Fine particulates | 0.02 | |
Nitrogen oxides and nitrogen oxides (summer) | 0.96 | |
VOCs and VOCs (summer) | 0.5 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Pharmaceutical and veterinary products production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 2,000 tonnes | 15 | |
More than 2,000 but not more than 5,000 tonnes | 50 | |
More than 5,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Plastic resins production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 2,000 tonnes | 25 | |
More than 2,000 but not more than 10,000 tonnes | 65 | |
More than 10,000 tonnes | 165 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 8 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Benzene | 0.5 | |
Fine particulates | 5.0 | |
Nitrogen oxides and nitrogen oxides (summer) | 3.0 | |
VOCs and VOCs (summer) | 8.5 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Plastics reprocessing (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual reprocessing capacity | Administrative fee units | |
Not more than 5,000 tonnes | 25 | |
More than 5,000 but not more than 10,000 tonnes | 65 | |
More than 10,000 tonnes | 165 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 8 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Benzene | 0.5 | |
Fine particulates | 5.0 | |
Nitrogen oxides and nitrogen oxides (summer) | 3.0 | |
VOCs and VOCs (summer) | 8.5 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Rubber products/tyres production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 5,000 tonnes | 50 | |
More than 5,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Soap and detergents production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 2,500 tonnes | 15 | |
More than 2,500 but not more than 5,000 tonnes | 50 | |
More than 5,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Soap and detergents (toxic substances) production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 2,500 tonnes | 15 | |
More than 2,500 but not more than 5,000 tonnes | 50 | |
More than 5,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Synthetic rubber production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 2,000 tonnes | 15 | |
More than 2,000 but not more than 5,000 tonnes | 50 | |
More than 5,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Toxic substance production (see clause 8 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 15 | |
More than 10,000 but not more than 25,000 tonnes | 50 | |
More than 25,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
CHEMICAL STORAGE | ||
Chemical storage waste generation (see clause 9 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee (but only if the activity is a scheduled activity under clause 9 (2) of Schedule 1 to the Act) | |
Annual volume of waste generated or stored | Administrative fee units | |
More than 5 but not more than 100 tonnes | 8 | |
More than 100 tonnes | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
General chemicals storage (see clause 9 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: kilolitres | |
2 | Administrative fee | |
Storage capacity | Administrative fee units | |
Not more than 5,000 kilolitres | 8 | |
More than 5,000 but not more than 100,000 kilolitres | 25 | |
More than 100,000 kilolitres | 65 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Petroleum products storage (see clause 9 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: kilolitres | |
2 | Administrative fee | |
Storage capacity | Administrative fee units | |
Not more than 5,000 kilolitres | 8 | |
More than 5,000 but not more than 100,000 kilolitres | 25 | |
More than 100,000 kilolitres | 65 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Benzene | 0.0005 | |
VOCs and VOCs (summer) | 0.05 | |
Water pollutants | Threshold factor | |
Nil | Not applicable |
COAL WORKS | ||
Coal works (see clause 10 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual handling capacity | Administrative fee units | |
Not more than 2,000,000 tonnes | 50 | |
More than 2,000,000 but not more than 5,000,000 tonnes | 135 | |
More than 5,000,000 tonnes | 335 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
COKE PRODUCTION | ||
Coke production (see clause 11 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual handling capacity | Administrative fee units | |
Not more than 100,000 tonnes | 65 | |
More than 100,000 tonnes | 165 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 11 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Benzene | 0.072 | |
Benzo(a)pyrene (equivalent) | 0.00073 | |
Coarse particulates | 0.45 | |
Fine particulates | 0.45 | |
Hydrogen sulfide | 0.002 | |
Nitrogen oxides and nitrogen oxides (summer) | 0.03 | |
Sulfur oxides | 0.4 | |
VOCs and VOCs (summer) | 0.83 | |
Water pollutants | Threshold factor | |
Oil and grease | 0.011 | |
Suspended solids | 0.13 | |
Total PAHs | 0.000032 | |
Total phenolics | 0.000032 |
COMPOSTING | ||
Composting (see clause 12 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual capacity to receive organics | Administrative fee units | |
Not more than 5,000 tonnes | 5 | |
More than 5,000 but not more than 50,000 tonnes | 15 | |
More than 50,000 tonnes | 50 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
CONCRETE WORKS | ||
Concrete works (see clause 13 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: cubic metres | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 13,000 cubic metres | 5 | |
More than 13,000 but not more than 25,000 cubic metres | 15 | |
More than 25,000 but not more than 50,000 cubic metres | 50 | |
More than 50,000 cubic metres | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
CONTAINER RECONDITIONING | ||
Container reconditioning (see clause 14 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual capacity to recondition, recover, treat or store | Administrative fee units | |
Any capacity | 50 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
CONTAMINATED SOIL TREATMENT | ||
Contaminated soil treatment (see clause 15 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual handling capacity | Administrative fee units | |
Any capacity | 50 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
CRUSHING, GRINDING OR SEPARATING | ||
Crushing, grinding or separating (see clause 16 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 but not more than 100,000 tonnes | 15 | |
More than 100,000 but not more than 500,000 tonnes | 50 | |
More than 500,000 but not more than 2,000,000 tonnes | 135 | |
More than 2,000,000 tonnes | 335 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
ELECTRICITY GENERATION | ||
Electricity generation (see clause 17 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: gigawatt-hours | |
2 | Administrative fee | |
Annual generating capacity | Administrative fee units | |
Not more than 450 gigawatt-hours (GWh) | 25 | |
More than 450 but not more than 1,000 gigawatt-hours (GWh) | 65 | |
More than 1,000 but not more than 4,000 gigawatt-hours (GWh) | 165 | |
More than 4,000 gigawatt-hours (GWh) | 420 | |
3 | Load-based fee (but only if the annual generating capacity exceeds 250 gigawatt-hours) | |
Generation of electrical power from coal | ||
Air pollutants | Threshold factor | |
Benzo(a)pyrene (equivalent) | 0.0036 | |
Coarse particulates | 80.0 | |
Fine particulates | 54.0 | |
Fluoride | 14.0 | |
Nitrogen oxides and nitrogen oxides (summer) | 2,700 | |
Sulfur oxides | 5,300 | |
Water pollutants | Threshold factor | |
Salt | 3.6 | |
Selenium | 0.14 | |
Suspended solids | 0.18 | |
Generation of electrical power from gas | ||
Air pollutants | Threshold factor | |
Nitrogen oxides and nitrogen oxides (summer) | 2,700 | |
Water pollutants | Threshold factor | |
Salt | 3.6 | |
Suspended solids | 0.18 | |
Generation of electrical power otherwise than from coal or from gas (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
ENERGY RECOVERY | ||
Energy recovery from general waste (see clause 18 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual capacity | Administrative fee units | |
Any capacity | 65 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Arsenic | 0.00005 | |
Benzene | 0.0000011 | |
Benzo(a)pyrene | 0.00002 | |
Fine particulates | 0.7 | |
Lead | 0.035 | |
Mercury | 0.003 | |
Nitrogen oxides and nitrogen oxides (summer) | 2.5 | |
Sulfur oxides | 0.07 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Energy recovery from hazardous or other waste (see clause 18 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual capacity | Administrative fee units | |
Any capacity | 65 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Arsenic | 0.00005 | |
Benzene | 0.0000011 | |
Benzo(a)pyrene | 0.00002 | |
Fine particulates | 0.7 | |
Lead | 0.035 | |
Mercury | 0.003 | |
Nitrogen oxides and nitrogen oxides (summer) | 2.5 | |
Sulfur oxides | 0.07 | |
Water pollutants | Threshold factor | |
Nil | Not applicable |
EXTRACTIVE ACTIVITIES | ||
Land-based extractive activity (see clause 19 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Extractive, processing or storage capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 but not more than 50,000 tonnes | 15 | |
More than 50,000 but not more than 100,000 tonnes | 50 | |
More than 100,000 but not more than 500,000 tonnes | 135 | |
More than 500,000 but not more than 2,000,000 tonnes | 335 | |
More than 2,000,000 tonnes | 600 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Water-based extractive activity (see clause 19 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: cubic metres | |
2 | Administrative fee | |
Extractive capacity | Administrative fee units | |
Not more than 30,000 cubic metres | 5 | |
More than 30,000 but not more than 50,000 cubic metres | 15 | |
More than 50,000 but not more than 100,000 cubic metres | 50 | |
More than 100,000 but not more than 500,000 cubic metres | 135 | |
More than 500,000 but not more than 2,000,000 cubic metres | 335 | |
More than 2,000,000 cubic metres | 600 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
HELICOPTER-RELATED ACTIVITIES | ||
Helicopter-related activity (see clause 20 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: flights | |
2 | Administrative fee | |
Annual flight movement capacity | Administrative fee units | |
Not more than 1,500 flights | 5 | |
More than 1,500 but not more than 5,000 flights | 15 | |
More than 5,000 flights | 50 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
IRRIGATED AGRICULTURE | ||
Irrigated agriculture (see clause 21 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: hectares | |
2 | Administrative fee | |
Total area of existing area of operations of irrigation corporation | Administrative fee units | |
Not more than 10,000 hectares | 15 | |
More than 10,000 but not more than 100,000 hectares | 50 | |
More than 100,000 hectares | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
LIVESTOCK INTENSIVE ACTIVITIES | ||
Animal accommodation (see clause 22 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Live weight capacity to accommodate | Administrative fee units | |
Not more than 25,000 tonnes | 5 | |
More than 25,000 but not more than 60,000 tonnes | 15 | |
More than 60,000 tonnes | 50 | |
Note— Live weight capacity is to be calculated either by using the actual live weight, or estimating live weight on the basis that 1 tonne live weight equals 2 cattle, 13 goats, 22 sheep, 2 horses, 5 deer, 17 emus, 13 kangaroos, 5 breeding sows, 17 porker or finisher pigs or 11 bacon pigs. | ||
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Bird accommodation (see clause 22 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Live weight capacity to accommodate | Administrative fee units | |
Not more than 375 tonnes | 5 | |
More than 375 but not more than 1,000 tonnes | 15 | |
More than 1,000 tonnes | 50 | |
Note— Live weight capacity is to be calculated either by using the actual live weight, or estimating live weight on the basis that 1 tonne live weight equals 555 layer chickens, 1,100 broiler chickens, 17 emus, 310 ducks, 165 geese or 110 turkeys. | ||
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Cattle, sheep or horse accommodation (see clause 22 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Live weight capacity to accommodate | Administrative fee units | |
Not more than 500 tonnes | 5 | |
More than 500 but not more than 2,500 tonnes | 15 | |
More than 2,500 tonnes | 50 | |
Note— Live weight capacity is to be calculated either by using the actual live weight, or estimating live weight on the basis that 1 tonne live weight equals 2 cattle, 13 goats, 2 horses or 22 sheep. | ||
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Dairy animal accommodation (see clause 22 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Live weight capacity to accommodate | Administrative fee units | |
Not more than 500 tonnes | 5 | |
More than 500 but not more than 1,000 tonnes | 15 | |
More than 1,000 tonnes | 50 | |
Note— Live weight capacity is to be calculated either by using the actual live weight, or estimating live weight on the basis that 1 tonne live weight equals 1.6 milking cows or 13 other dairy animals. | ||
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Pig accommodation (see clause 22 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Live weight capacity to accommodate | Administrative fee units | |
Not more than 250 tonnes | 5 | |
More than 250 but not more than 500 tonnes | 15 | |
More than 500 tonnes | 50 | |
Note— Live weight capacity is to be calculated either by using the actual live weight, or estimating live weight on the basis that 1 tonne live weight equals 5 breeding sows, 62 weaner pigs, 31 grower pigs, 17 porker or finisher pigs or 11 bacon pigs. | ||
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
LIVESTOCK PROCESSING ACTIVITIES | ||
General animal products production (see clause 23 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 100,000 tonnes | 5 | |
More than 100,000 tonnes | 15 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Greasy wool or fleece processing (see clause 23 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Any capacity | 5 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Rendering or fat extraction (see clause 23 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 4,000 tonnes | 5 | |
More than 4,000 tonnes | 15 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Slaughtering or processing animals (see clause 23 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 tonnes | 15 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Tanneries or fellmongeries (see clause 23 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 10,000 tonnes | 5 | |
More than 10,000 tonnes | 15 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
LOGGING OPERATIONS | ||
Logging operations (see clause 24 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual capacity | Administrative fee units | |
Any capacity | 5,500 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
MARINAS AND BOAT REPAIRS | ||
Boat construction/maintenance (dry/floating docks) (see clause 25 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual handling capacity | Administrative fee units | |
Any capacity | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Boat construction/maintenance (general) (see clause 25 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual handling capacity | Administrative fee units | |
Any capacity | 50 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Boat mooring and storage (see clause 25 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual handling capacity | Administrative fee units | |
Any capacity | 15 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
METALLURGICAL ACTIVITIES | ||
Aluminium production (alumina) (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Any capacity | 420 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Coarse particulates | 5 | |
Fine particulates | 12 | |
Fluoride | 1 | |
Nitrogen oxides and nitrogen oxides (summer) | 0.2 | |
Sulfur oxides | 20 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Aluminium production (scrap metal) (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 65 | |
More than 10,000 tonnes | 165 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.048 | |
Fine particulates | 0.066 | |
Fluoride | 1 | |
Nitrogen oxides and nitrogen oxides (summer) | 4 | |
Sulfur oxides | 9.6 | |
VOCs and VOCs (summer) | 0.68 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Iron or steel production (iron ore) (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Any capacity | 2,650 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Benzene | 0.0011 | |
Benzo(a)pyrene (equivalent) | 0.003 | |
Coarse particulates | 0.47 | |
Fine particulates | 0.38 | |
Hydrogen sulfide | 0.018 | |
Nitrogen oxides and nitrogen oxides (summer) | 3.81 | |
Sulfur oxides | 6.6 | |
VOCs and VOCs (summer) | 7 | |
Water pollutants | Threshold factor | |
Arsenic | 0.0091 | |
Cadmium | 0.0018 | |
Chromium | 0.0054 | |
Copper | 0.0036 | |
Lead | 0.0018 | |
Mercury | 0.000091 | |
Oil and grease | 0.015 | |
Selenium | 0.00091 | |
Suspended solids | 0.24 | |
Zinc | 0.0091 | |
Iron or steel production (scrap metal) (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 65 | |
More than 10,000 tonnes | 165 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.085 | |
Fine particulates | 0.77 | |
Nitrogen oxides and nitrogen oxides (summer) | 1.95 | |
Sulfur oxides | 3.38 | |
VOCs and VOCs (summer) | 0.09 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Metal coating (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual capacity to coat metal | Administrative fee units | |
Not more than 100,000 tonnes | 15 | |
More than 100,000 but not more than 1,000,000 tonnes | 50 | |
More than 1,000,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Metal processing (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 100,000 tonnes | 15 | |
More than 100,000 but not more than 500,000 tonnes | 50 | |
More than 500,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Metal waste generation (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee (but only if the activity is a scheduled activity under clause 26 (2) (b) of Schedule 1 to the Act) | |
Annual volume of waste generated or stored | Administrative fee units | |
More than 5 but not more than 100 tonnes | 8 | |
More than 100 tonnes | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Non-ferrous metal production (ore concentrates) (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Any capacity | 660 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Arsenic | 0.03 | |
Coarse particulates | 0.33 | |
Fine particulates | 0.49 | |
Lead | 0.06 | |
Mercury | 0.03 | |
Sulfur oxides | 230 | |
Water pollutants | Threshold factor | |
Arsenic | 0.0003 | |
Cadmium | 0.0003 | |
Chromium | 0.0003 | |
Copper | 0.0026 | |
Lead | 0.03 | |
Mercury | 0.0003 | |
Selenium | 0.0003 | |
Suspended solids | 0.78 | |
Zinc | 0.02 | |
Non-ferrous metal production (scrap metal) (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 65 | |
More than 10,000 tonnes | 165 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.011 | |
Fine particulates | 0.033 | |
Lead | 0.002 | |
Nitrogen oxides and nitrogen oxides (summer) | 0.57 | |
Sulfur oxides | 0.99 | |
VOCs and VOCs (summer) | 2.28 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Scrap metal processing (see clause 26 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 100,000 tonnes | 15 | |
More than 100,000 but not more than 500,000 tonnes | 50 | |
More than 500,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
MINERAL PROCESSING | ||
Mineral processing (see clause 27 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 but not more than 100,000 tonnes | 15 | |
More than 100,000 but not more than 500,000 tonnes | 50 | |
More than 500,000 but not more than 2,000,000 tonnes | 135 | |
More than 2,000,000 tonnes | 335 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Mineral waste generation (see clause 27 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee (but only if the activity is a scheduled activity under clause 27 (2) of Schedule 1 to the Act) | |
Annual volume of waste generated or stored | Administrative fee units | |
More than 5 but not more than 100 tonnes | 8 | |
More than 100 tonnes | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
MINING FOR COAL | ||
Mining for coal (see clause 28 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 500,000 tonnes | 50 | |
More than 500,000 but not more than 2,000,000 tonnes | 135 | |
More than 2,000,000 but not more than 3,500,000 tonnes | 335 | |
More than 3,500,000 but not more than 5,000,000 tonnes | 600 | |
More than 5,000,000 tonnes | 850 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
MINING FOR MINERALS | ||
Mining for minerals (see clause 29 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 30,000 tonnes | 5 | |
More than 30,000 but not more than 50,000 tonnes | 15 | |
More than 50,000 but not more than 100,000 tonnes | 50 | |
More than 100,000 but not more than 500,000 tonnes | 135 | |
More than 500,000 but not more than 2,000,000 tonnes | 335 | |
More than 2,000,000 but not more than 5,000,000 tonnes | 600 | |
More than 5,000,000 tonnes | 850 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
PAPER OR PULP PRODUCTION | ||
Paper or pulp production (see clause 30 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 150,000 tonnes | 65 | |
More than 150,000 tonnes | 165 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Coarse particulates | 0.39 | |
Fine particulates | 1.49 | |
Nitrogen oxides and nitrogen oxides (summer) | 3.51 | |
Water pollutants | Threshold factor | |
BOD | 5.55 | |
Salt | 3.0 | |
Suspended solids | 8.35 | |
Total nitrogen | 0.1 | |
Total phosphorous | 0.001 | |
Zinc | 0.13 | |
Paper or pulp waste generation (see clause 30 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual volume of waste generated or stored | Administrative fee units | |
More than 5 but not more than 100 tonnes | 8 | |
More than 100 tonnes | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
PETROLEUM AND FUEL PRODUCTION | ||
Crude oil/shale oil production (see clause 31 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 25 | |
More than 10,000 but not more than 200,000 tonnes | 65 | |
More than 200,000 but not more than 500,000 tonnes | 165 | |
More than 500,000 tonnes | 660 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 31 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Benzene | 0.004 | |
Benzo(a)pyrene (equivalent) | 0.005 | |
Fine particulates | 0.2 | |
Hydrogen sulfide | 0.031 | |
Nitrogen oxides and nitrogen oxides (summer) | 0.5 | |
Sulfur oxides | 0.6 | |
VOCs and VOCs (summer) | 0.4 | |
Water pollutants | Threshold factor | |
BOD | 0.14 | |
Oil and grease | 0.12 | |
Suspended solids | 0.36 | |
Total PAHs | 0.07 | |
Total phenolics | 0.27 | |
Natural gas/methane production (see clause 31 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 25 | |
More than 10,000 but not more than 200,000 tonnes | 65 | |
More than 200,000 but not more than 500,000 tonnes | 165 | |
More than 500,000 tonnes | 660 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 31 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Benzene | 0.004 | |
Benzo(a)pyrene (equivalent) | 0.005 | |
Fine particulates | 0.2 | |
Hydrogen sulfide | 0.031 | |
Nitrogen oxides and nitrogen oxides (summer) | 0.5 | |
Sulfur oxides | 0.6 | |
VOCs and VOCs (summer) | 0.4 | |
Water pollutants | Threshold factor | |
BOD | 0.14 | |
Oil and grease | 0.12 | |
Suspended solids | 0.36 | |
Total PAHs | 0.07 | |
Total phenolics | 0.27 | |
Petroleum products and fuel production (see clause 31 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual production capacity | Administrative fee units | |
Not more than 10,000 tonnes | 25 | |
More than 10,000 but not more than 200,000 tonnes | 65 | |
More than 200,000 but not more than 500,000 tonnes | 165 | |
More than 500,000 tonnes | 660 | |
3 | Load-based fee (but only if the activity is a scheduled activity under clause 31 (2) of Schedule 1 to the Act) | |
Air pollutants | Threshold factor | |
Benzene | 0.004 | |
Benzo(a)pyrene (equivalent) | 0.005 | |
Fine particulates | 0.2 | |
Hydrogen sulfide | 0.031 | |
Nitrogen oxides and nitrogen oxides (summer) | 0.5 | |
Sulfur oxides | 0.6 | |
VOCs and VOCs (summer) | 0.4 | |
Water pollutants | Threshold factor | |
BOD | 0.14 | |
Oil and grease | 0.12 | |
Suspended solids | 0.36 | |
Total PAHs | 0.07 | |
Total phenolics | 0.27 |
PRINTING, PACKAGING AND VISUAL COMMUNICATIONS | ||
Printing, packaging and visual communications waste generation (see clause 32 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual volume of waste generated or stored | Administrative fee units | |
More than 5 but not more than 100 tonnes | 8 | |
More than 100 tonnes | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
RAILWAY SYSTEMS ACTIVITIES | ||
Railway systems activities (see clause 33 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual capacity | Administrative fee units | |
Any capacity | 50 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
RESOURCE RECOVERY | ||
Recovery of general waste (see clause 34 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of material recovered | Administrative fee units | |
General waste | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Recovery of hazardous and other waste (see clause 34 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of material recovered | Administrative fee units | |
Hazardous and other waste | 32 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Recovery of waste oil (see clause 34 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual recovery capacity | Administrative fee units | |
Not more than 1,000 tonnes | 25 | |
More than 1,000 tonnes | 65 | |
3 | Load-based fee (but only if the annual capacity exceeds 20,000 tonnes) | |
Air pollutants | Threshold factor | |
Lead | 0.2 | |
VOCs and VOCs (summer) | 0.05 | |
Water pollutants | Threshold factor | |
Oil and grease | 4.8 | |
Recovery of waste tyres (see clause 34 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of material recovered | Administrative fee units | |
Waste tyres | 12 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
ROAD CONSTRUCTION | ||
Road construction (see clause 35 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: kilometres | |
2 | Administrative fee | |
Design length of road to be constructed, widened or re-routed | Administrative fee units | |
Not more than 10 kilometres | 50 | |
More than 10 but not more than 30 kilometres | 135 | |
More than 30 kilometres | 335 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
SEWAGE TREATMENT | ||
Sewage treatment (see clause 36 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: megalitres | |
2 | Administrative fee | |
Annual maximum volume of discharge | Administrative fee units | |
Not more than 20 megalitres | 5 | |
More than 20 but not more than 100 megalitres | 8 | |
More than 100 but not more than 1,000 megalitres | 25 | |
More than 1,000 but not more than 5,000 megalitres | 65 | |
More than 5,000 but not more than 10,000 megalitres | 165 | |
More than 10,000 but not more than 20,000 megalitres | 300 | |
More than 20,000 but not more than 30,000 megalitres | 420 | |
More than 30,000 megalitres | 2,650 | |
3 | Load-based fee (but only if the maximum annual volume of sewage that the relevant licence authorises to be discharged exceeds 219 megalitres) | |
Processing by small plants (less than 10,000 megalitres annual capacity) | ||
Air pollutants | Threshold factor | |
Nil | Not applicable | |
Water pollutants | Threshold factor | |
BOD | 10 | |
Oil and grease | 2 | |
Total nitrogen | 10 | |
Total phosphorous | 0.3 | |
Suspended solids | 15 | |
Processing by large plants (more than 10,000 megalitres annual capacity) | ||
Air pollutants | Threshold factor | |
Nil | Not applicable | |
Water pollutants | Threshold factor | |
BOD | 10 | |
Cadmium | 0.00005 | |
Chromium | 0.0025 | |
Copper | 0.01 | |
Lead | 0.0005 | |
Mercury | 0.00005 | |
Oil and grease | 2 | |
Selenium | 0.0025 | |
Suspended solids | 15 | |
Total nitrogen | 10 | |
Pesticides and PCBs | 0.00012 | |
Total phosphorous | 0.3 | |
Zinc | 0.012 |
SHIPPING IN BULK | ||
Shipping in bulk (see clause 37 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual capacity to load and unload | Administrative fee units | |
Not more than 100,000 tonnes | 15 | |
More than 100,000 but not more than 500,000 tonnes | 50 | |
More than 500,000 tonnes | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
STERILISATION ACTIVITIES | ||
Sterilisation activities (see clause 38 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual capacity | Administrative fee units | |
Any capacity | 32 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
WASTE DISPOSAL (APPLICATION TO LAND) | ||
Waste disposal by application to land (see clause 39 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual capacity | Administrative fee units | |
Any capacity | 32 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
WASTE DISPOSAL (THERMAL TREATMENT) | ||
Thermal treatment of general waste (see clause 40 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual capacity | Administrative fee units | |
Any capacity | 65 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Arsenic | 0.00005 | |
Benzene | 0.0000011 | |
Benzo(a)pyrene | 0.00002 | |
Fine particulates | 0.7 | |
Lead | 0.035 | |
Mercury | 0.003 | |
Nitrogen oxides and nitrogen oxides (summer) | 2.5 | |
Sulfur oxides | 0.07 | |
Water pollutants | Threshold factor | |
Nil | Not applicable | |
Thermal treatment of hazardous and other waste (see clause 40 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: tonnes | |
2 | Administrative fee | |
Annual capacity | Administrative fee units | |
Any capacity | 65 | |
3 | Load-based fee | |
Air pollutants | Threshold factor | |
Arsenic | 0.00005 | |
Benzene | 0.0000011 | |
Benzo(a)pyrene | 0.00002 | |
Fine particulates | 0.7 | |
Lead | 0.035 | |
Mercury | 0.003 | |
Nitrogen oxides and nitrogen oxides (summer) | 2.5 | |
Sulfur oxides | 0.07 | |
Water pollutants | Threshold factor | |
Nil | Not applicable |
WASTE PROCESSING (NON-THERMAL TREATMENT) | ||
Non-thermal treatment of general waste (see clause 41 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of waste treated | Administrative fee units | |
General waste | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Non-thermal treatment of hazardous and other waste (see clause 41 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of waste treated | Administrative fee units | |
Hazardous and other waste | 32 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Non-thermal treatment of waste tyres (see clause 41 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of waste treated | Administrative fee units | |
Waste tyres | 12 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
WASTE STORAGE | ||
Waste storage (see clause 42 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of waste stored | Administrative fee units | |
Hazardous waste, restricted solid waste, liquid waste, clinical and related waste and asbestos waste | 32 | |
Waste tyres | 12 | |
Other types of waste | 16 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
WOOD OR TIMBER MILLING OR PROCESSING | ||
Wood or timber milling or processing (see clause 43 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: cubic metres | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 50,000 cubic metres | 5 | |
More than 50,000 but not more than 100,000 cubic metres | 15 | |
More than 100,000 but not more than 200,000 cubic metres | 50 | |
More than 200,000 cubic metres | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
WOOD PRESERVATION | ||
Wood preservation (see clause 44 (1) of Schedule 1 to the Act) | ||
1 | Units of measure: cubic metres | |
2 | Administrative fee | |
Annual processing capacity | Administrative fee units | |
Not more than 10,000 cubic metres | 15 | |
More than 10,000 but not more than 30,000 cubic metres | 50 | |
More than 30,000 cubic metres | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
MOBILE PLANT ACTIVITIES | ||
Mobile plant activity (see clause 46 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of activity | Administrative fee units | |
Any capacity | 5 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
MOBILE WASTE PROCESSING | ||
Mobile waste processing (see clause 47 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of activity | Administrative fee units | |
Any capacity | 32 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
TRANSPORT OF WASTE | ||
Transport of hazardous and other waste (see clause 48 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual capacity to transport | Administrative fee units | |
Any capacity | 4 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Transport of waste tyres (see clause 48 (1) of Schedule 1 to the Act) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Annual capacity to transport | Administrative fee units | |
Any capacity | 4 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
MISCELLANEOUS WATER ACTIVITIES | ||
Miscellaneous licensed discharge to waters (wet weather only), meaning any activity (other than a scheduled activity) in relation to which a licence to discharge pollutants to waters during or immediately following periods of wet weather (but not at any other time) has been granted under the Act | ||
1 | Units of measure: megalitres | |
2 | Administrative fee | |
Maximum annual volume of discharge authorised by licence (calculated by multiplying maximum allowable daily discharge by 50) | Administrative fee units | |
Not more than 3 megalitres | 5 | |
More than 3 but not more than 15 megalitres | 15 | |
More than 15 but not more than 150 megalitres | 50 | |
More than 150 megalitres | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) | |
Miscellaneous licensed discharge to waters (at any time), meaning any activity (other than a scheduled activity) in relation to which a licence to discharge pollutants to waters has been granted under the Act | ||
1 | Units of measure: megalitres | |
2 | Administrative fee | |
Maximum annual volume of discharge authorised by licence | Administrative fee units | |
Not more than 20 megalitres | 5 | |
More than 20 but not more than 100 megalitres | 15 | |
More than 100 but not more than 1,000 megalitres | 50 | |
More than 1,000 megalitres | 135 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
OTHER ACTIVITIES NOT OTHERWISE LISTED | ||
Other activities, meaning any activity (other than a scheduled activity or miscellaneous water activity) | ||
1 | Units of measure (not applicable) | |
2 | Administrative fee | |
Type of activity | Administrative fee units | |
Any capacity | 5 | |
3 | Load-based fee (there are no assessable pollutants and therefore no load-based fee in relation to this activity) |
sch 1: Am 30.4.1999; 25.6.1999; 2.6.2000; 16.6.2000; 30.3.2001; 1.6.2001; 2007 (295), Sch 1 [13] [14]. Subst 2008 (109), Sch 2 [9].
Schedule 2 Membership and procedure of Load-Based Licensing Technical Review Panel
(Clause 43)
1 Chairperson
(1) One of the members of the Review Panel is to be appointed by the Minister as Chairperson of the Review Panel. The appointment may be made at the time the person is appointed as a member or after that appointment.(2) A person vacates the office of Chairperson if the person:(a) ceases to be a member, or(b) resigns that office by instrument in writing addressed to the Minister, or(c) is removed from that office under this clause.(3) The Minister may at any time remove a person from the office of Chairperson.
2 Deputies of members
(1) The Minister may, from time to time, appoint a person to be the deputy of a member of the Review Panel, and the Minister may revoke any such appointment.(2) In the absence of a member, the member’s deputy:(a) may, if available, act in the place of the member, and(b) while so acting, has all the functions of the member and is to be taken to be a member.(3) The deputy of a member who is the Chairperson does not (because of this clause) have the member’s functions as Chairperson.(4) A person while acting in the place of a member is entitled to be paid such allowances as the Minister may from time to time determine in respect of the person.
3 Terms of office
Subject to this Schedule, a member of the Review Panel holds office for such period (not exceeding 3 years) as is specified in the member’s instrument of appointment, but is eligible (if otherwise qualified) for re-appointment.
4 Allowances
A member of the Review Panel is entitled to be paid such allowances as the Minister from time to time determines in respect of the member.
5 Vacancy in office of member
(1) The office of a member of the Review Panel becomes vacant if the member:(a) dies, or(b) completes a term of office and is not re-appointed, or(c) resigns the office by instrument in writing addressed to the Minister, or(d) is removed from office under this clause, or(e) is absent from 4 consecutive meetings of the Review Panel of which reasonable notice has been given to the member personally or in the ordinary course of post, except on leave granted by the Review Panel or unless, before the expiration of 4 weeks after the last of those meetings, the member is excused by the Review Panel for having been absent from those meetings, or(f) becomes bankrupt, applies to take the benefit of any law for the relief of bankrupt or insolvent debtors, compounds with his or her creditors or makes an assignment of his or her remuneration for their benefit, or(g) becomes a mentally incapacitated person, or(h) is convicted in New South Wales of an offence that is punishable by penal servitude or imprisonment for 12 months or more or is convicted elsewhere than in New South Wales of an offence that, if committed in New South Wales, would be an offence so punishable.(2) The Minister may remove a member from office at any time.
6 Filling of vacancy in office of member
If the office of a member of the Review Panel becomes vacant, a person may, subject to this Regulation, be appointed to fill the vacancy.
7 Disclosure of pecuniary interests
(1) If:(a) a member of the Review Panel has a direct or indirect pecuniary interest in a matter being considered or about to be considered at a meeting of the Review Panel, andthe member must, as soon as possible after the relevant facts have come to the member’s knowledge, disclose the nature of the interest at a meeting of the Review Panel.(b) the interest appears to raise a conflict with the proper performance of the member’s duties in relation to the consideration of the matter,(2) A disclosure by a member at a meeting of the Review Panel that the member:(a) is a member, or is in the employment, of a specified company or other body, or(b) is a partner, or is in the employment, of a specified person, oris a sufficient disclosure of the nature of the interest in any matter relating to that company or other body or to that person that may arise after the date of the disclosure and that is required to be disclosed under subclause (1).(c) has some other specified interest relating to a specified company or other body or to a specified person,(3) Particulars of any disclosure made under this clause must be recorded by the Review Panel in a book kept for the purpose and that book must be open at all reasonable hours to inspection by any person on payment of the fee (if any) determined by the Review Panel.(4) After a member has disclosed the nature of an interest in any matter, the member must not, unless the Minister or the Review Panel otherwise determines:(a) be present during any deliberation of the Review Panel with respect to the matter, or(b) take part in any decision of the Review Panel with respect to the matter.(5) For the purpose of the making of a determination by the Review Panel under subclause (4), a member who has a direct or indirect pecuniary interest in a matter to which the disclosure relates must not:(a) be present during any deliberation of the Review Panel for the purpose of making the determination, or(b) take part in the making by the Review Panel of the determination.(6) A contravention of this clause does not invalidate any decision of the Review Panel.
8 General procedure
The procedure for the calling of meetings of the Review Panel and for the conduct of business at those meetings is, subject to this Regulation and to any direction of the Minister, to be as determined by the Review Panel.
9 Quorum
The quorum for a meeting of the Review Panel is a majority of the members for the time being of the Review Panel.
10 Presiding member
(1) The Chairperson of the Review Panel or, in the absence of the Chairperson, another member elected to chair the meeting by the members present is to preside at a meeting of the Review Panel.(2) The person presiding at any meeting of the Review Panel has a deliberative vote and, in the event of an equality of votes, has a second or casting vote.
11 Voting
A decision supported by a majority of the votes cast at a meeting of the Review Panel at which a quorum is present is the decision of the Review Panel.
12 Minutes of meetings
The Review Panel is required to keep minutes of proceedings at its meetings.
Schedule 3 Prescribed matter for the definition of water pollution
(Clause 52)
1
Any animal matter of any description, including (but not limited to) carcasses of animals, parts or remains of animals, offal, flesh and bones.
2
Any plant matter of any description, including (but not limited to) vegetable or fruit wastes, leaves, grass, trees, wood, sawdust, shavings, chips, bark or other forest products or refuse.
3
Any ashes, soil, earth, mud, stones, sand, clay or similar inorganic matter.
4
Any washings or spoil from any mineral processing or extractive operation, from any dredging operation or from any other industrial, agricultural or commercial activity.
5
Any ballast.
6
Any excreta, manure or urine, or any waste from an on-site human waste storage facility or treatment device.
7
Any matter of an infectious nature.
8
Any scrap metal, glass, junk, paper, plastic, rubbish, vehicle or vehicle tyres, any industrial waste and any refuse of any other description.
9
Any oil, grease or flammable liquid of any description.
10
Any thermal waste (being any liquid which, after being used in or in connection with any activity, is more than 2 degrees Celsius hotter or colder than the water into which it is discharged).
11
Any matter that causes biochemical oxygen demand.
12
Any matter that causes chemical oxygen demand.
13
Any liquid that contains suspended or dissolved solids.
14
Any gas other than oxygen.
15
Any methylene blue active substance.
16
Any matter that contains faecal coliform or faecal streptococci.
17
Any matter that has a pH value of less than 6.5 or more than 8.5.
18
Any pesticide (within the meaning of the Pesticides Act 1978).
19
Any poisonous substance of any description.
20
Any radioactive substance.
21
Any substance classified as dangerous goods under the Australian Code for the Transport of Dangerous Goods by Road and Rail.
22
Any substance listed in Schedule 10 to the Water Board (Corporatisation) Act 1994.
23
Any substance listed in the National Occupational publications entitled List of Designated Hazardous Substances published in March 1994 by the National Occupational Health and Safety Commission [NOHSC: 10005 (1994)].
24
Any chemical toxicant for which guidelines are prescribed by the publication entitled Australian Water Quality Guidelines for Fresh and Marine Waters published in November 1992 by the Australian and New Zealand Environment and Conservation Council.
25
Any of the following substances:
arsenic, barium, boron, cadmium, chloride, chromium (hexavalent), copper, cyanide, fluoride, iron (dissolved), lead, manganese (dissolved), mercury, selenium, silver, uranyl ion or zinc.
26
Any matter that contains any nitrogen, sulphur, phenolic or phosphorous compound.
27
Any matter that contains matter referred to above.
Schedule 4 Forms relating to noise abatement directions
(Clause 58)
(Section 280)
MAGISTRATE’S RECORD OF COMPLAINT REQUESTING THE ISSUE OF A WARRANT TO ENTER PREMISES
Details of the complaint
On ............... at ..... am/pm, I, the undersigned Magistrate, received a complaint alleging that the complainant had been denied entry to premises at ............................................................
The complaint was made in person*/by telephone*.
The complaint was made by ...................., a police officer stationed at ............................................................
The complainant caused the complaint to be transmitted to me by ...................., a police officer stationed at ....................*
Further details of the complaint are set out on the other side of this page.
Grounds of the complaint
The complainant stated their belief that:
• offensive noise was being emitted from the premises*
• offensive noise had, within the 7 days preceding the complaint, been emitted from the premises*.
The police officer requested the grant of a warrant because the officer believed it was necessary to enter the premises immediately in order:
• to give a noise abatement direction in relation to offensive noise emitted from the premises*
• to investigate whether a noise abatement direction has been contravened*.
Outcome of consideration of the complaint
After considering the complaint I was satisfied that there were reasonable grounds for that belief.
The grounds on which I relied to justify my finding that there were reasonable grounds for that belief are as follows:
............................................................
............................................................
............................................................
............................................................
............................................................
............................................................
............................................................
............................................................
Details of grant of warrant
I have granted my warrant authorising and requiring the complainant to enter the premises and:
• to give a noise abatement direction*
• to investigate whether a noise abatement direction has been contravened*.
The warrant was granted on ............... at ..... am/pm
Signed ............................................................
(Magistrate) |
* Delete if inapplicable.
(Overleaf)
Details of Complaint
1.Names of persons involved (if known):2.Location of premises:3.Name of civilian informant (if known):4.The complainant police officer believed that:(a) offensive noise was being emitted from the premises*(b) offensive noise had, within the past 7 days, been emitted from the premises*.* Delete if inapplicable.5.Other information obtained by complainant police officer:(a) Personal observations by police (e.g. noise from the house is being emitted, type of noise, etc):(b) Civilian informant’s information (indications that noise has recently been emitted):(c) Any other information cited as grounds for the belief of the complainant by reason of which the warrant was requested and granted:6.The officer had been denied entry to the premises, details of which (including anything said or done) are:
(Section 280)
NOTICE OF GRANT OF WARRANT TO ENTER PREMISES
A warrant has been granted to enter premises at ............................................................
The warrant was granted on the basis of a complaint made by a police officer stationed at .................... police station.
The warrant was granted at ..... am/pm on ...............
The warrant was granted by .................... a Magistrate of the Local Court.
The warrant was granted subject to the following additional terms: *
......................... Signature of complainant police officer
* Delete if inapplicable.
(Section 280)
IMPORTANT INFORMATION FOR OCCUPIERS CONCERNING THE WARRANT
A warrant has been granted by a Magistrate.
The warrant gives the authority and power to police to enter premises and:
(a) to give a noise abatement direction (which is a direction under the Protection of the Environment Operations Act 1997 to cause the emission of offensive noise to stop or to stop making or contributing to offensive noise), or
(b) to investigate whether a noise abatement direction has been breached.
Reasons for the issue of the warrant
A member of the police force has made a complaint to a Magistrate that the police officer was denied entry to the premises and that the member of the police force believed:
(a) that offensive noise was being emitted from the premises (or that offensive noise had been emitted within the previous 7 days), and
(b) that it was necessary for a police officer to enter the premises immediately in order to give a noise abatement direction in relation to offensive noise emitted from the premises or to investigate whether a noise abatement direction has been contravened.
The Magistrate was satisfied that there were reasonable grounds for that belief.
Details of the warrant
The police officer who was the complainant should have prepared a form containing details of:
(a) the address of the premises the subject of the warrant, and
(b) the name of the Magistrate who granted the warrant, and
(c) the name of the police officer, and
(d) the time at which the warrant was granted.
You should have been given that form by the police officer who entered the premises
Expiry
The warrant must be executed as soon as practicable after the time it is granted.
The warrant must be executed within 24 hours after the time it was granted.
The warrant may be executed at any time during the day or night.
Use of force
The police may use such force as is necessary for the purpose of entering any premises.
This may include breaking open any door.
Any force used must be reasonably necessary.
Limitations on the powers conferred
Only functions and powers authorised under the warrant or by the Act authorising the issue of the warrant may be performed.
The police officer is not authorised to stay on your premises any longer than is necessary.
Schedule 5 Open coastal waters
(Clause 20)
Open coastal waters for the purposes of clause 20 are ocean waters east of the natural coast line of New South Wales, defined as follows:(1) The natural coast line is defined by a line drawn along the high water mark of the sea.
(2) Where an estuary meets the coast, the natural coast line is defined as follows (unless paragraph (3) applies):(a) if an estuary has two break walls at the confluence with the South Pacific Ocean, by a line drawn across the easternmost extremity of both break walls,(b) if an estuary has only one break wall, by a line drawn from the easternmost extremity of the break wall to the northern or southern extremity of the high water mark on the opposite bank,(c) if an estuary enters the South Pacific Ocean and there are no defined points available, by a line drawn across the entrance between the easternmost extremity of the drying points on each bank.
(3) In relation to the following waters, the natural coast line is defined as follows:(a) Port Stephens—by a line drawn between the southern extremity of Yacaaba Point to the northern extremity of Tomaree Point,(b) Broken Bay—by a line drawn from the southern extremity of Box Head to the northern extremity of Barrenjoey Head,(c) Port Jackson—by a line drawn from the southern extremity of North Head to the northern extremity of South Head,(d) Botany Bay—by a line drawn from Endeavour Light to the northern extremity of Sutherland Point,(e) Port Hacking—by a line drawn from the southernmost extremity of Hungry Point to the northernmost extremity of Cabbage Tree or Pulpit Point,(f) Jervis Bay—by a line drawn from the southeastern point of Point Perpendicular to the southeastern point of Bowen Island thence to the northeastern point of Governor Head,(g) Wogonga River—by a line drawn northwest across the entrance from the northernmost extremity of Wogonga Head,(h) Batemans Bay—by a line drawn from the southwestern extremity of Square Point to the northernmost extremity of Observation Point.