Division 3 Work carried out by owners corporation
117   Provision of amenities and services to lot
An owners corporation may enter into an agreement with an owner or occupier of a lot to provide amenities or services to the lot or to the owner or occupier of the lot.
118   Window safety devices—child safety
(1)  An owners corporation for a strata scheme to which this section applies must ensure that there are complying window safety devices for all windows of each building in the strata scheme that are windows to which this section applies.
Maximum penalty—5 penalty units.
(2)  An owners corporation is to carry out work related to its functions under this section at its own expense and may, for the purposes of this section, carry out work on any part of the parcel.
(3)  An owner of a lot in a strata scheme to which this section applies may install a complying window safety device on a window to which this section applies (other than a window on another owner’s lot).
(4)  An owner of a lot who installs a window safety device under this section must—
(a)  repair any damage caused to any part of the common property by the installation of the device, and
(b)  ensure that the device is installed in a competent and proper manner and has an appearance, after it has been installed, in keeping with the appearance of the building.
(5)  An owners corporation or an owner of a lot may carry out work authorised by this section despite any other provision of this Act, the regulations or any by-law of the scheme.
(6)  The regulations may make provision for or with respect to the following—
(a)  the strata schemes and windows to which this section applies,
(b)  the devices or other things that are complying window safety devices for the purposes of this section,
(c)  notification to the owners corporation by owners who install window safety devices.
(7)  A regulation may apply this section to a window located on any part of a parcel.
119   Work to rectify certain defects
(1)  An owners corporation for a strata scheme may carry out work that is necessary to rectify any of the following defects—
(a)  any structural defect in any part of a building comprised in a lot in the scheme that affects or is likely to affect the support or shelter provided by that lot for another lot in the building or the common property,
(b)  any defect in any pipe, wire, cable or duct that provides, or through which passes, any water, sewage, drainage, gas, electricity, garbage, artificially heated or cooled air, heating oil or other service (including telephone, internet, radio or television services) within a lot.
(2)  An owners corporation may carry out the work at its own expense if the cost of the work cannot be recovered from some other person.
120   Owners corporation may carry out work required to be carried out by others
(1) Work required by public authority If an owner of a lot in a strata scheme fails to carry out work that is required to be carried out under a notice given to the owner by a public authority, the owners corporation may carry out the work and recover the cost of carrying out the work from the owner or any person who, after the work is carried out, becomes the owner.
(2) Work required to be carried out under term or condition of by-law If a person who is the owner, mortgagee or covenant chargee in possession, tenant or occupier of a lot in the strata scheme fails to carry out work that is required to be carried out by the person under a term or condition of a by-law of the scheme, the owners corporation may carry out the work and recover the cost of carrying out the work from that person, the owner of the lot (if the person is not the owner) or any person who, after the work is carried out, becomes the owner of that lot.
(3) Work that is duty of owner or occupier to carry out If a person who is the owner, mortgagee or covenant chargee in possession, tenant or occupier of a lot in the strata scheme fails to carry out work in order to remedy a breach of a duty imposed by Part 8, the owners corporation may carry out the work and recover the cost of the work from that person.
(4) Work required to be carried out under order If a person fails to carry out work required to be carried out under an order made under this Act, the owners corporation may carry out the work and recover the cost of carrying out the work from the person against whom the order was made.
(5) Recovery of costs as a debt The costs incurred by an owners corporation in carrying out any work referred to in this section may be recovered by the owners corporation as a debt.
121   Provision of letterbox
(1)  An owners corporation must construct and maintain at or near the street alignment of the parcel a letterbox suitable to receive mail and other documents.