Contents (2018 - 480)
Skip to content
Water Management (General) Regulation 2018
Current version for 7 February 2020 to date (accessed 10 April 2020 at 07:08)
Part 9 Division 9
Division 9 Miscellaneous
224   Supply of plans
On application by an owner or an owner’s agent, a water supply authority must issue a plan showing the point of connection to its sewerage system of any land.
225   Information to accompany applications under section 305
For the purposes of section 305(2) of the Act, an application for a certificate of compliance for development must be accompanied—
(a)  by information as to whether or not the development is the subject of development consent or a complying development certificate under the Environmental Planning and Assessment Act 1979, and
(b)  if it is so subject, by a copy of the development consent or complying development certificate.
226   Development that may be subject to section 306 requirements
For the purposes of section 306(1) of the Act, the following kinds of development are prescribed as development to which that section applies—
(a)  the erection, enlargement or extension of a building or the placing or relocating of a building on land,
(b)  the subdivision of land,
(c)  the change of use of land or of any building situated on the land.
227   Members of Cobar Water Board
For the purposes of clause 22(2)(b)(ii) of Schedule 5 to the Act, Peak Gold Mines Pty Ltd is prescribed as a mining company that can nominate a member of the Cobar Water Board in place of Goldcorp Asia Pacific Pty Ltd.