202   Persons who are to be provided with copies or notice of reports
(1)  A building inspector must give a copy of an interim report or a final report to the following persons not later than 14 days after completing the report—
(a)  the developer,
(b)  the owners corporation, if the initial period has ended,
(c)  the Secretary,
(d)  the builder responsible for any defective building work identified in the report.
(2)  An owners corporation must give written notice to the owners of lots in the strata scheme of the receipt of an interim report or a final report on building work in connection with the scheme not later than 14 days after receiving the report.
(3)  The notice must contain the particulars, if any, prescribed by the regulations for the purposes of this section.
Maximum penalty—5 penalty units.