Wentworth Local Environmental Plan 2011
Current version for 10 July 2020 to date (accessed 6 August 2020 at 03:37)
Part 7 Clause 7.2
7.2   Essential services
(1)  This clause applies to land in the following zones—
(a)  Zone RU5 Village,
(b)  Zone R5 Large Lot Residential,
(c)  Zone B6 Enterprise Corridor,
(d)  Zone IN1 General Industrial,
(e)  Zone IN2 Light Industrial.
(2)  Development consent must not be granted to development unless the consent authority is satisfied that any of the following services that are essential for the proposed development are available or that adequate arrangements have been made to make them available when required—
(a)  the supply of water,
(b)  the supply of electricity,
(c)  the disposal and management of sewage,
(d)  stormwater drainage or on-site conservation,
(e)  suitable road access.
(3)  This clause does not apply to development for the purpose of providing, extending, augmenting, maintaining or repairing a public utility infrastructure.