105   Definitions
In this Division—
biosolids treatment facility, sewage reticulation system, sewage treatment plant, sewerage system and water recycling facility have the same meanings as in the Standard Instrument.
Northside Storage Tunnel means—
(a)  a tunnel running from Thorn Street, Hunters Hill to the North Head Sewage Treatment Plant, Manly, and
(b)  a branch tunnel to Scotts Creek, and
(c)  branch bores to two outlets at Tarban Creek, namely, the Huntley’s Point submain and the Woolwich submain, and
(d)  a branch shaft to South Willoughby, and
(e)  a branch tunnel to Shelly Beach.
prescribed zone means any of the following land use zones or a land use zone that is equivalent to any of those zones—
(a)  RU1 Primary Production,
(b)  RU2 Rural Landscape,
(c)  RU4 Primary Production Small Lots,
(d)  IN1 General Industrial,
(e)  IN3 Heavy Industrial,
(f)  SP1 Special Activities,
(g)  SP2 Infrastructure.